Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
There are still 4 open projects in the programme, and at the time of reporting things were looking positive for all of these. The latest Wiki upgrade had been successfully deployed to Live in late June. This was further testament to the good work done by the project team, and was hugely helped by their flexibility in working out of standard hours. The JIRA upgrade was still in planning, and being managed by our student intern. The SOA upgrade (COM043) had gotten over the reported issues in Test, and was ready to be deployed to Live in early July. And, on the back of the resolution of these issues, the IDM database upgrade (COM045) was being readied for migration to Test, with new milestones being drawn up and the eventual delivery being moved back again into 19/20.
However, while COM046 and COM047 can now advance, respectively, towards closure and build (in Dev), the latter two projects have hit issues again with the problems encountered when the SOA upgrade was deployed into Live, then rolled back. This is still being analysed and the final impact on COM043 and COM045 is still to be determined.
RAG Status and Forward Look

Resources

Section Two: Projects Not Started
| Project Info | Project Manager's Commentary | ||
|---|---|---|---|
|
|
Section Three: Projects in Progress
| Project Info | Project Manager's Commentary | ||||||||||||||||||||||||
| COM043 SOA Upgrade to v12
Compliance Milestones
RAG Status AMBER |
Report by Adam Wadee for June 2019 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||
|
Compliance Milestones
RAG Status AMBER. Project delayed due to COM043 SOA upgrade. |
Report by Chris Konczak for June 2019 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||
|
Compliance Milestones Milestones
RAG Status GREEN
|
Report by Chris Konczak for June 2019 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||
|
COM047 Milestones
RAG Status GREEN
|
Report by Yiwei Jing for June 2019 Achievements
Issues
Next steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|
Project closed - Closure Report
|
|
| COM042 - GDPR Preparation for Applications | Project closed - Closure Report |
| COM044 - Serengeti Annual Upgrade | Project closed - Closure Report |
| COM048 Bi-Annual CalSync Upgrade | Project withdrawn - Decision |
| COM036 - BI Business Objects Upgrade | Project closed - Closure Report |
| COM041 Decommission legacy Windows hosting | Project closed - Closure Report |
Section Five: Actions/Notes from monthly programme meeting
| Project | Action / Notes | Responsibility | Status |
|---|---|---|---|