Report for May 2019

Report Date
May 2019

Section One: Programme Commentary, RAG and Resources Update

Programme Commentary

This month's report starts with another closure of a long-running piece of work - the decommissioning of our old Windows hosting service under project COM041. Getting the project completed is a testament to the persistent and patient work of the project team.

This leaves 3 current projects. One of them, COM046 (Wiki Upgrade) is progressing pretty much as planned, with a deployment to LIVE planned for the end of this month. This is obviously dependent on the successful completion of the user testing that is currently way, but no issues have yet been encountered.

The two other projects are intertwined, with COM045 awaiting the deployment to LIVE in COM043 before it can advance to Integration & Acceptance, However, reported issues with the latter project have impacted the progress of the IDM Database Upgrade project, and so both projects have had to report as Amber this month with these problems delaying progress. It is anticipated that a solution will soon be available (early June) and that both projects can therefore be replanned and get back on track. The project teams on both projects are to be commended for their resilience in managing these problems.

Finally, the JIRA Upgrade (COM047) will be initiated at the start of June with the arrival of Yiwei JIng (our student intern) who will be the PM on this one.

 

RAG Status and Forward Look

Resources

 

 Section Two: Projects Not Started

Project Info     Project Manager's Commentary
COM047  Annual JIRA Upgrade
Scheduled to start in June 2019

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary
COM043 SOA Upgrade to v12

Compliance

Milestones

Delivery 25-June-2019 (TBC)
Deployment Sign Off Review 12-July-2019 (TBC)
Close 26-July-2019 (TBC)

RAG Status

AMBER

Report by Adam Wadee for May 2019

Achievements

  • During pre-go live testing we encountered issues with the SOA server config which has delayed our deployment to live (see Issue 8 for further info).
  • The project team are currently working on the issues and we have informed key stakeholders about the go live postponement.
  • We are working with Student Systems to identify a suitable go live date.

Issues

  • Go live date delayed and milestones revised.

Next steps

  • Resolve all issues.

  • Agree go live date.

  • Deploy to live.

RAG Commentary
Issues have been encountered during pre-go live testing which have delayed our go live date in May. The delay is impacting the IDM Database Upgrade project (COM045) pushing it into 19/20. There is no student impact. The project team are currently working on the issues and expect to have them resolved by w/c 10 June.

COM045 IDM Database Upgrade

Compliance

Milestones

DEV build sign off 14-Jun-2019
Integration testing sign off 02-Jul-2019
Acceptance testing sign off 22-Jul-2019
Deploy to LIVE 01-Aug-2019
Deployment Sign Off Review 15-Aug-2019
Project Closure 29-Aug-2019

RAG Status

AMBER. Project delayed due to COM043 SOA upgrade.

Report by Chris Konczak for May 2019

Achievements in Last Period

  • No further progress on project during May due to waiting for the TEST environment to be released from COM043 SOA upgrade project.
  • Milestones have been replanned and project re-resourced from the next available COM043 deployment date communicated at the time which was 11/06/2019.

Issues

  • Continuing issues with COM043 have prevented progress with DEV sign off and with the migration to TEST on COM045. The project had been replanned and resourced to start after 11/06/2019. COM045 PM is waiting on confirmation that SOA will be deployed on 11/06/2019 before submitting the milestone changes to WIS, or to replan COM045 if a new deployment date is confirmed.
  • The project will carryover into 2019/20. Current estimate is 8.5 days

Next Steps

  • DEV sign off
  • Commence the TEST upgrade
  • Begin integration testing

COM046 - Annual WIKI upgrade

Compliance

Milestones

Milestones

Acceptance sign off 14-Jun-2019
Deploy to LIVE 26-Jun-2019
Deployment Sign Off Review (DSOR) 08-Jul-2019
Closure 29-Jul-2019

 

RAG Status

GREEN

 

Report by Chris Konczak for May 2019

Achievements in Last Period

  • Test upgrade completed
  • Integration testing signed off
  • UAT period has begun, ending on 14/06/2019. No issues have been reported so far.

Issues

  • None

Next Steps

  • UAT sign off agreed
  • Deployment to LIVE

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

COM040 - JIRA Upgrade

Project closed - Closure Report

 

COM042 - GDPR Preparation for Applications  Project closed - Closure Report
COM044 - Serengeti Annual Upgrade Project closed - Closure Report
COM048 Bi-Annual CalSync Upgrade Project withdrawn - Decision
COM036 - BI Business Objects Upgrade Project closed - Closure Report
COM041 Decommission legacy Windows hosting Project closed - Closure Report

Section Five: Actions/Notes from monthly programme meeting 

Project Action / Notes Responsibility    Status
       
       