Report for April 2019
- Report Date
- April 2019
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
The long-running COM036 has now been closed, and COM041 is now due to be closed at the end of May. There is a short delay to this because of PM availability to work on the closure. The decommissioning tasks for COM036 (not completed) have been picked up under INF137. This month also saw the closure of COM044. slightly ahead of schedule and under budget.
COM043 now has a go-live date of 14th May, with the UAT being completed successfully and signed off. There has been some overspend on this one and the PM will be preparing a PICCL to cover this shortly.
The delay to COM043 has meant that the milestones for COM045 have had to be pushed back, with delivery into Live now expected in early July. Resources and support have been secured. COM046 is continuing pretty much as planned, with the Live deployment due in mid-June. Again, resources are booked for this.
Finally, we have our intern starting soon and he will be able to get started on the JIRA upgrade in June.
RAG Status and Forward Look

Resources

Section Two: Projects Not Started
| Project Info | Project Manager's Commentary | ||
|---|---|---|---|
|
Scheduled to start in June 2019 |
Section Three: Projects in Progress
| Project Info | Project Manager's Commentary | ||||||||||||
|
COM036 BI - Business Objects Upgrade Compliance Milestones Completed RAG Status BLUE |
Report by Chris Konczak for April 2019 Achievements in Last PeriodProject closed: Closure Report |
||||||||||||
|
COM041 Decommission legacy Windows hosting Compliance
Milestones
RAG Status AMBER |
Report by Tim Gray for April 2019 Achievements in Last Period
Issues
Next steps
|
||||||||||||
| COM043 SOA Upgrade to v12
Compliance Milestones
RAG Status GREEN |
Report by Adam Wadee for April 2019
Achievements in Last Period
Issues
Next steps
|
||||||||||||
|
Compliance Milestones
RAG Status AMBER (Resolved). Project delayed due to COM043 SOA upgrade experiencing infrastructure issues on all environments. |
Report by Chris Konczak for April 2019 Achievements in Last Period
Issues
Next Steps
|
||||||||||||
|
Compliance Milestones Milestones
RAG Status GREEN
|
Report by Chris Konczak for April 2019 Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|
Project closed - Closure Report
|
|
| COM042 - GDPR Preparation for Applications | Project closed - Closure Report |
| COM044 - Serengeti Annual Upgrade | Project closed - Closure Report |
| COM048 Bi-Annual CalSync Upgrade | Project withdrawn - Decision |
| COM036 - BI Business Objects Upgrade | Project closed - Closure Report |
Section Five: Actions/Notes from monthly programme meeting
| Project | Action / Notes | Responsibility | Status |
|---|---|---|---|