Report for January 2019
- Report Date
- January 2019
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
There has been progress with the BI Tools upgrade (COM036) in which a lot of the reported issues have been successfully addressed (with some good work by Service Management and others) and the project overspend is also being resolved. There is still a problem with Explorer and investigations into this are still being carried out.
Projects COM041 and COM043 are both continuing more or less as planned, though both have had tweaks to milestones. They are both still expected to deliver in the first few months of 2019.
The Serengeti Update (COM044) and IDM Database Upgrade (COM045) have both recently passed their respective planning milestones, with the DEV environment now being prepared for the former, and similar work planned for the latter in late February.
The Wiki upgrade (COM046) is still in planning stage, with this expected by the end of February. The Bi-Annual CalSync Upgrade has also been in planning, but it now looks like this project will be withdrawn for 18-19 and the budget returned to the programme. This is good news for the planned JIRA Upgrade as it looked like this might be withdrawn. This is still to be planned for July/August.
RAG Status and Forward Look

Resources

Section Two: Projects Not Started
| Project Info | Project Manager's Commentary | ||
|---|---|---|---|
|
Scheduled to start in June 2019 |
Section Three: Projects in Progress
| Project Info | Project Manager's Commentary | ||||||||||||||
|
COM036 BI - Business Objects Upgrade Compliance Milestones
RAG Status AMBER |
Report by Chris Konczak for January 2019 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||
|
COM041 Decommission legacy Windows hosting Compliance
Milestones
RAG Status GREEN |
Report by Tim Gray for January 2019 Achievements in Last Period
Issues
Next steps
|
||||||||||||||
| COM043 SOA Upgrade to v12
Compliance Milestones
RAG Status GREEN |
Report by Adam Wadee for January 2019 Achievements
Issues
Next steps
|
||||||||||||||
|
COM044 Serengeti Database Annual Migration /Upgrade Compliance Milestones
RAG Status GREEN |
Report by Anne Mathison for January 2019 Achievements
Issues
Next Steps
|
||||||||||||||
|
Compliance Milestones
RAG Status GREEN |
Report by Chris Konczak for January 2019 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||
|
Compliance Milestones
RAG Status GREEN
|
Report by Chris Konczak for January 2019 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||
|
COM048 Bi-Annual CalSync Upgrade Compliance Milestones
RAG Status
GREEN |
Report by Anne Mathison for January 2019 Achievements
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|
Project closed - Closure Report
|
|
| COM042 - GDPR Preparation for Applications | Project closed - Closure Report |
Section Five: Actions/Notes from monthly programme meeting
| Project | Action / Notes | Responsibility | Status |
|---|---|---|---|