Report for June 2018
- Report Date
- June 2018
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
In this reporting period work has continued on all active projects. The BI Annual Upgrade remains RED due to ongoing performance issues on DEV. These are still being investigated and the project team believe that a July go live is no longer feasible. The Grouper Upgrade, was deployed into Live, and should now close. The SOA Upgrade has changed direction; the GDPR Readiness project has also delivered, and there has been a change of PM on COM041 with the departure of Megan Graham. A PM resource has been identified for the JIRA Upgrade and this is now expected to start in June.
RAG Status and Forward Look

Resources

Section Two: Projects Not Started
| Project Info | Project Manager's Commentary |
|---|---|
| N/A |
|
Section Three: Projects in Progress
| Project Info | Project Manager's Commentary | ||||||||||||||||
|
COM036 BI - Business Objects Upgrade Compliance Milestones
RAG Status RED
|
Report by Chris Konczak for June 2018 Achievements
Issues
Next Steps
|
||||||||||||||||
|
Compliance Milestones 29-June-18 Build Review and Acceptance 12-July-2018 Closure RAG Status GREEN |
Report by Adam Wadee for June 2018 Achievements
Issues
Next steps
|
||||||||||||||||
|
Compliance Milestones
RAG Status GREEN
|
Report by Chris Konczak for June 2018 Achievements
Issues
Next Steps
|
||||||||||||||||
|
Compliance Milestones
RAG Status Green |
Report by David Watters for June 2018 Achievements
Issues
Next steps
|
||||||||||||||||
|
COM041 Decommission legacy Windows hosting Compliance
Milestones
RAG Status GREEN |
Report by Tim Gray for June 2018 Achievements This Period
Issues
Next Steps
|
||||||||||||||||
|
COM042 GDPR Preparation for Applications Compliance Milestones
RAG Status AMBER |
Report by Emma McNab for June 2018 Achievements
Issues
Next Steps
Amber: Change - Closure milestone has slipped. due to availability of Project Manager. Project Manager undertaking review of milestones however project is expected to close within 2017/18. |
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|
Compliance |
Report by Chris Konczak This project was closed on 08/08/17 (WIS Notes 09/09/17) Please see the Completion Report for further information |
|
Compliance |
Report by Tim Gray This project was closed on 14/08/17 (WIS Notes 11/08/17) Please see the Completion Report for further information |
|
Rollout Academic Timetable Integration with Office 365 Calendar Discretionary |
Report by Chris Copner This project was closed on 18/08/17 (WIS Notes 18/08/17) Please see the Completion Report for further information |
|
Serengeti Document Management Server Upgrade Compliance |
Report by Morna Findlay This project was closed on (WIS Notes 23/03/18) Please see the Completion Report for further information. |
|
Compliance |
Report by David Watters Project was closed on 22/06/18 (WIS notes 22/06/18) Please see the completion report for further information |
Section Five: Actions/Notes from monthly meeting held on 15/05/2018
| Project | Action / Notes | Responsibility | Status |
|---|---|---|---|
| COM036 |
The migration tool is not fit for purpose. SC to await feedback from vendor today if not successful then escalate through AC PJ to speak to Mark McG re figures on the technical issues. PJ suggested stress test on LIVE with 5/6 users - SC to speak to AMcF to organise. CK to progress weekend work - has everyone responded? Have ITI confirmed their availability for DNS change? Project team to discuss if weekend work is really necessary? |
SC/AC PJ/SC/AMcF TG/CK |
|
| COM038 |
Project should aim to complete as much infrastructure work this year as possible to utilise the available resources. |
AW |
|
| COM039 | License issue to be clarified - TG follow up with CK/SK | TG/CK | |
| COM040 | JIRA Upgrade project to be moved to start in June. Forward Look to be updated and PRICCL raised. | DW |