February 2017

Report Date
February 2017

 

 

Codesort descending Programme Owner and Manager Commentary RAG Manager Status Stage
CIS001

VOIP Replacement for University Telephones

Preparing report for the project board - aiming to send out by 24/3. Currently showing underspend of £330K.

GREEN Maurice Franceschi In Progress Execute
CIS002

Extend Core Network (Resilient links)

Expecting to have contract signed and kit ordered by 17/3. Expectation is 60-80 days for review and deployment June/July). Dave to update milestones from best estimate .  

RED David Graham In Progress Execute
CIS003

Access Control Door Infrastructure Upgrade - Procure and Install

Assigning Alan Sloan to this. Starting April.  

  Alan Boyd Not Started Initiate
CIS004

Network Strategic Review

Budget revised and ready to submit that to Annual Planning. Project board on 24/3, desirable outcome is signed-off strategy.  

GREEN Maurice Franceschi In Progress Analyse
CIS005

Standard Template for IT New Builds and Refurbishments.

Almost completed. Final tweaks by Ian Vaughn then handing over to Maurice for sign-off and delivery.

 

AMBER Maurice Franceschi In Progress Execute
CIS007 2016 Clearing BLUE Iain Moore-McLaughlin Closed Close
CIS008

Network Security Controls

Kirsty currently not at work due to family concerns. David G to talk to Kerry to write up high level requirements document as we aim for end of planning 31/3.

 

GREEN Kirsty Waddell In Progress Plan
CIS009

Network Infrastructure Procurement

Hoping to start in April. However, we have a strong dependency on approval of revised budget. Competative dialogue will be used as our procurement approach.

 

  Maurice Franceschi Not Started Initiate
CIS010

Network Infrastructure Deployment 2018

 

  Maurice Franceschi Not Started Initiate
CIS011

Infoblox deployment

David will speak to Sam and Mark to see how to progress this. David likely to PM.  

  Maurice Franceschi Not Started Initiate