Report for October 2019
- Report Date
- October 2019
Report for September 2019
- Report Date
- During October
The progress of the Delivered Catering procurement project has stalled during the completion of the question sets whilst awaiting confirmation of the interface requirements to the new Core Finance system
Forward Look


Resource Position





Section Two: Projects Not Started
There are no further scheduled projects for 2018-19
| Project Info | Programme Managers Commentary |
|
AP90-005
|
Delivered Catering Implementation |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||
|
Delivered Catering Procurement Category: Discretionary Sponsor Funded Milestones
Rag Status: Green |
Report by Andy Stewart for September 2019 Achievements This Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
Section Five: Programme Risks
| Date Updated | Risk Ref. | Programme Risks | RAG Status | Risk Owner |
| 10/09/19 | 9 | Programme Management budget for 2019-20 being exceeded | Green | Andrew Stewart |
| 02/07/19 | 10 | Completion of Programme Activity within 2019-20 | Green | Claire Barnish |
Section Six : Programme Meeting Minutes
The minutes from the programme meetings since July 2018 can be located on the Accommodation Catering and Events SharePoint site