Report for September 2019
- Report Date
- September 2019
Report for September 2019
- Report Date
- July 2019
During September
- ACS042 - Delivered Catering Procurement - project planning has been completed
Forward Look

Resource Position

Section Two: Projects Not Started
There are no further scheduled projects for 2018-19
| Project Info | Programme Managers Commentary |
|
AP90-005
|
Delivered Catering Implementation |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||
|
Delivered Catering Procurement Category: Discretionary Sponsor Funded Milestones
Rag Status: Green |
Report by Andy Stewart for September 2019 Achievements This Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
Section Five: Programme Risks
| Date Updated | Risk Ref. | Programme Risks | RAG Status | Risk Owner |
| 10/09/19 | 9 | Programme Management budget for 2019-20 being exceeded | Green | Andrew Stewart |
| 02/07/19 | 10 | Completion of Programme Activity within 2019-20 | Green | Claire Barnish |
Section Six : Programme Meeting Minutes
The minutes from the programme meetings since July 2018 can be located on the Accommodation Catering and Events SharePoint site
| Attachment | Size |
|---|---|
| 24.38 KB | |
| 25.49 KB | |
| 26.28 KB | |
| 23.05 KB |