Report for July 2019

Report Date
July 2019

During July

  • There has been little activity within the programme this month as the programme of activity for 2018-19 has been completed.

Forward Look 

Resource Position 

 

Section Two: Projects Not Started

 

There are no  further scheduled projects for 2018-19

 

Project Info Programme Managers Commentary

 

 

 

 

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

AP89-901

Salto Door Access

 

ACS041 

Kx Infrastructure Upgrades 

Project closure report 

Project closure was formally approved by WIS on 28th June 2019

 

Section Five: Programme Risks

Date Updated Risk Ref. Programme Risks RAG Status Risk Owner
02/07/19 7 Completion of Programme Activity within 2018-19 Closed  Andrew Stewart
02/07/19 8 Programme Management budget for 2018-19 being exceeded Red  Andrew Stewart

Section Six : Programme Meeting Minutes

The minutes from the programme meetings since July 2018 can be located on the Accommodation Catering and Events SharePoint site

 

 

 

 

 

 

Documentation

Not available.