Report for April 2019
- Report Date
- April 2019
During April,
- The Kx Infrastructure Upgrade project (ACS041) has successfully delivered the Database Upgrades into the live environment
- Annual Planning estimation meeting held for the planned projects for 2019-20
Forward Look

Resource Position

Section Two: Projects Not Started
There are no further scheduled projects for 2018-19
| Project Info | Programme Managers Commentary |
|
|
|
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||
|
Kx Infrastructure Consolidation Category: Discretionary Sponsor Funded
Milestones have been re-planned
RAG Status: Amber |
Report by Andy Stewart for April 2019 Achievements in the last period
Issues
Next steps
RAG CommentaryRequirement to re-plan deployment of live of Phase 2 Database Servers migration due to technical issues resulting from post go-live of Phase 1 Application Webservers (13/03/19) and UAT delays. Phase 2 database Servers subsequently successfully deployed on 25/04/19. Project running five weeks behind planned schedule |
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|
AP89-901 Salto Door Access |
Section Five: Programme Risks
| Date Updated | Risk Ref. | Programme Risks | RAG Status | Risk Owner |
| 10/05/19 | 7 | Completion of Programme Activity within 2018-19 | Green | Andrew Stewart |
| 10/05/19 | 8 | Programme Management budget for 2018-19 being exceeded | Red | Andrew Stewart |
Section Six : Programme Meeting Minutes
The minutes from the programme meetings since July 2018 can be located on the Accommodation Catering and Events SharePoint site
| Attachment | Size |
|---|---|
| 34.17 KB | |
| 29.72 KB | |
| 25.71 KB | |
| 28.78 KB | |
| 20.87 KB | |
| 29.32 KB | |
| 21.22 KB | |
| 28.27 KB | |
| 25.66 KB | |
| 28.27 KB | |
| 21.42 KB | |
| 33.15 KB | |
| 43.19 KB | |
| 23.58 KB | |
| 28.19 KB | |
| 21.37 KB |