November 2019

Report Date
November 2019

Achievements this Month

  • Project Closed on 11 November 2019

Project Status
RAG Status
Overall
BLUE
RAG Commentary
Project Closed 11/11/19
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Change Commentary
No change
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.