October 2019
- Report Date
- October 2019
Achievements in Last Period:
- Analysis started re new subject coding and implementation from JACS to HECoS- Review with stakeholders
- System changes progressed (SITS, and downstream systems)
Issues:
- Project manager has left the project (conflict with Core Systems)- being covered by programme manager- delay to complete brief and plan
- delay to agree subject coding structure. BA progressing for agreement with keys stakeholders
- Dependency with Tribal changes required in SITS to suit new code structure. Need firm date of code change release. Being raised by Dev team leader
Next Steps:
- complete brief and plan of work/milestones
- articulate dependencies
Milestones:
- Brief completion 28 Oct 2019
-hard deadline for implementation end Jan 20
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days