Report for October 2019
- Report Date
- October 2019
Section One: Programme Commentary, RAG and Resources Update
Commentary
The overall status of the HRS Programme is GREEN , with both the GDPR project and the HESA project reporting GREEN this month.
During October:
- The GDPR project reached an agreement to close the project without implementing the proposed solution, but with agreement to document it; and the project is set to close next month
- The HESA project completed its final submission, and is set to close next month
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Forward Look - October 2019
Resources to end October 2019
Section Two: Projects Not Started and Current Programme Allocations
Project Info | Programme Manager's Commentary and Start of Year Position | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
AP90-033 HESA Staff Return 19/20 to be started later this academic year - approx March 2020 |
The budget for the HRS programme for 2019/20 is set at 247 days from core allocation; this breaks down as 16 days for programme/portfolio management, 220 days for the HESA projects and 11 days for the contingency.
|
Section Three: Projects in Progress
Project Info |
Project Managers Commentary | ||||||||||||||||||||||||||||||||||||||||
HRS096 GDPR Updates for eRecruitment Milestones
RAG Status: GREEN
|
Report by Ken Miller for October 2019Achievements this Period
IssuesNext Steps
|
||||||||||||||||||||||||||||||||||||||||
HRS097 HR/HESA Staff Return 2018/19
Milestones :
RAG Status :GREEN
|
Report by Anne Mathison for October 2019Achievements
Issues
Next Steps
Project RAG status of GREEN |
Section Four: Closed or Withdrawn Projects
06-Dec-2019 |