Achievements in Last Period:
- Project initiated
- Project Brief written and issued for review.
Issues:
Next Steps:
- Preparations for deployment of v5.16.1 to the development environment.
- Approved budget
- 50.0 days
- Activity this month
- 4.5 days
- Activity this year
- 4.5 days
- Activity to date
- 4.5 days
- Estimate to complete current year
- 45.5 days
- Estimate to complete future years
- 0.0 days