Impact

Priority and Funding

Project category is compliance

Initial project priority is Normal.

Project is Core Funded

Impact and Dependencies

The HR, Payroll & Pensions application and database requires to be patched annually to deliver the statutory Tax Year End patches.

In a normal year, the pre-requisite patches will be applied through DEV, TEST and LIVE from November with the Tax Year End patches being progressed through February and sometimes March

There are a number of projects which will be working on the same DEV, TEST and LIVE environments in the same timescale as PPP01?. They may also require the same IS Apps and Business resources to work on them. This needs to be taken into account during planning for PPP01? and the other projects. At this time, the projects identified are as follows:

Project

Plan

Impact/Dependency

HRS097 HESA Staff Return - 19/20

In Live with no issues. Final commit milestone to be completed. Will be signed off and closed in Nov 2019

Should have little or no impact

HRS096 GDPR Updates

Planned to close by end November 2019

Need to plan work around each other

FIN131 Pension Scheme Changes Not started.  Likely to be people availability which will delay progress of affected project

 

Project Risks

(Please copy and paste from Risk Log)

There should be no risks assigned to the PM

New risk – Limited availability of experienced resources Core is now taking some from 3-June-2019. This has been included in RISK 13 and should be included in the 19/20 project.

Ref Title Initial Risk Current Risk Status Management Approach Risk Owner Date of Last Review
1 Core System - Critical Resouce secondments RED AMBER Open Reduce Craig Henderson 30-Oct-2019
2 Risk that patching involves too much downtime during the working day GREEN GREEN Open Reduce Graham Mechan 14-Oct-2019
3

Impact on resource of wider business continuity issues including winter weather and industrial action

GREEN GREEN Open Reduce Craig Henderson 30-Oct-2019
4 Dev Tech resoucing not available when required GREEN GREEN Open Reduce Mark Lang 30-Oct-2019
5 Apps Support are not available when required GREEN GREEN Open Reduce Anne Graham 14-Oct-2019
6 Project Manager is not available when required GREEN GREEN Open Reduce Emma McNab 30-Oct-2019
7 Human Resources resource may not be available for testing when required GREEN GREEN Open Reduce Deborah Kilgallon 14-Oct-2019
8 Payroll and Pensions may not be available for testing when required GREEN GREEN Open Reduce Graham Mechan 14-Oct-2019
9 Risk that no payroll technical support has been agreed to support project GREEN AMBER Open Reduce Craig Henderson 31-Oct-2019
10

Robustness of UAT and Sign Off

AMBER AMBER Open Reduce Craig Henderson 31-Oct-2019

 

Project Info

Not available.

Documentation

Not available.