September Report 2019

Report Date
September 2019

Achievements this period

  • Closing Report was drafted and discussed with Programme Manager and ITI
  • Clarification of Closing Report finalised with ITI

Issues

  • Change of Closing Milestone to 11th October 2019 (was 13/09/2019) was submitted and approved by WIS on Friday,  20/09/2019

Next Steps

  • Closing Report to be finalised and signed off by SRA and Communications
  • Closing Project
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
50.0 days
Activity this month
4.7 days
Activity this year
9.2 days
Activity to date
41.8 days
Estimate to complete current year
1.5 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.