Report for September 2019

Report Date
September 2019

Achievements this period

  • Scenarios for supplier evaluation demonstrations agreed by team, via a user story workshop

  • Contextual metrics document reviewed with draft text added

  • Updated procurement strategy in line with project team feedback

  • Clarifications provided on mandatory requirements

Issues

  • Requirements Specification milestone has passed, but expected to be completed in first week of October in time for ITT approval
  • Procurement strategy still to be signed off by Director of Procurement;  this will be resolved early in October, in advance of the Invitation to Tender (ITT)
  • Discussion in progress to agree how to incorporate the requirement for 'encryption at rest' - clarification being sought from Information Security Team

Next Steps

  • Sign off procurement strategy
  • Finalise the mandatory requirements and contextual metrics to be put forward to bidders to demonstrate; alongside the evaluation process and weightings.
  • Complete requirements specification and ITT documentation for tender; ready for approval by the Core Systems Programme Board
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
120.0 days
Activity this month
4.8 days
Activity this year
14.6 days
Activity to date
45.5 days
Estimate to complete current year
74.6 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.