Report for September 2019

Report Date
September 2019

Achievements in Last Period:

  • Project Brief Signed-off.
  • Project team and third party all engaged.
  • Work is progressing ahead of plan with early indications of achieving deployment on 17/10 rather than originally scheduled 15/11.

Issues:

  • None.

Next Steps:

  • Preparations for implementation.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
20.0 days
Activity this month
6.5 days
Activity this year
6.5 days
Activity to date
6.5 days
Estimate to complete current year
13.5 days
Estimate to complete future years
0.0 days