Report for Aug 2019

Report Date
August 2019

Report compiled by  Jamie Thin (IS Apps Programme Manager) 

for Jim McGeorge (USG), Tracey Slaven (GASP) ,Theresa Merrick (CAM) , Niall Bradley (CAM),  Steven Ross (CAM) , Paddy Corscadden (SDS),Gael Campbell (SDS) ,Ronnie Millar( SCS) ,Jane Johnston (SRA), Rebecca Gaukroger(SRA), Ailsa Vamplew (SRA), Lesley Stokes (SRA), Laura Cattell (SRA) , Clare MacKay (SRA) , Shellagh Green (Careers) , Damon Querry (RIS), Rena Gertz (Data Protection Officer), Sara Cranston (Records Management), Karsten Moerman (IAD) , Jon Turner (IAD) , Sarah Macallister (IAD) , Andrew Crossland (Student Systems) , Rena Gertz (GaSP)  and other interested business area owners.

 

Section One: Programme Commentary, RAG and Resources Update

Commentary

 

The STU programme is GREEN, as all in-progress projects are GREEN

 

--

Programme Risks ( RED & AMBER)

   

UG & PG Degree finder-Business Continuity Plan to be updated by Dec 2019( STU260 - CAM UG & PG Degree Finders) AMBER             Niall Bradley
     
Existing 'Mobility Online' solution will not be decommissioned by SEP SAS0014/ SAS016 Work & Study Away project ( need to be kept for in progress Student exchanges and to continue to support Staff exchanges going forward)  AMBER Jim McGeorge

 

RAG & Forward Look to end of Aug 2019

 

 

STU RAG to end of Aug 2019

 

 

Resources to end of Aug 2019

 

 

STU Actual spend to end of Aug 2019

 

 

 

 

Section Two: Projects Not Started

 

AP90-039 CAM- Support for Compliance

 50 days core for potential compliance work, 14 days transferred to STU260 security work,

balance available = 36 days for rest of 19-20

 

Section Three: Projects in Progress

 

Project Info

Project Managers Commentary

STU257 Privacy Impact Assessment Tool

Category: Compliance

Milestones

The revised (projected) milestones still require to be confirmed with the project sponsor.

Target Date  Title
03-Jul-2019 Deployment to Live
22-Jul-2019 Deployment Sign-Off
16-Aug-2019 Closure

RAG Status

GREEN

  Report by Andy Stewart for July 2019

Achievements this period

  • Go-Live
    • Application is now live and being used across the University
  • DPIA
    • Completed actual DPIA for the actual Assessment Automation application
  • Accessibility
    • eQIA completed and published
    • Details of Accessibility report forwarded to the supplier for consideration
  • SSO
    • Investigations towards implementing SSO are on-going
    • Completed Regular Data Feed request form and forwarded to golden copy owners for approval
  • SMTP
    • Investigations towards implementing SMTP are on-going

Issues

  • Whilst investigations are on-going regarding SSO and SMTP, this has been hampered by the lack of technical resource availability

Next steps

  • Accessibility 
    • Review supplier response to Accessibility Report
  • System Configuration  
    • Confirm Regular Data Feed approval regarding SSO 
    • Complete technical implementation for SSO and SMTP
    • Complete Email configuration
  • Service Management to clarify service arrangements and SLA with the business 
  • Complete project closure

 

STU260 CAM  Degree Finders - Options Appraisal 

Category:  Compliance

Milestones:

Complete Build in DEV for Security Strengthening of the UG & PG Degree finders 09-Sep-2019
Complete Integration Testing in TEST for Security Strengthening of the UG & PG Degree finders 19-Sep-2019
UAT sign-off complete for Security Strengthening of UG & PG Degree finder 27-Sep-2019
Deploy to LIVE - WP1 - Security Strengthening of UG & PG Degree Finders 03-Oct-2019
Project closure 25-Oct-2019

RAG Status:

GREEN

 Report by Chris Konczak for August 2019

Achievements this period

  • Planning signoff achieved
  • Dev Tech resource secured to begin in September to complete DEV and TEST
  • Go-Live date agreed for after the change freeze in October
  • Milestone replan agreed

Issues

  • None

Next Steps

  • Complete DEV and TEST
  • Integration and UAT sign off
  • Deploy to LIVE after change freeze
  • DSOR

 

STU265 - G-Cloud replacement of FOI Request planning tool

Category:  Compliance

Milestones

Milestone Date
Product Procurement 30-Aug-2019
Product Implementation 25-Oct-2019
User Acceptance Testing - Sign Off 08-Nov-2019
Go Live 22-Nov-2019
Deployment Sign Off 06-Dec-2019
Migration of Historic Data 13-Dec-2019
Legacy ColdFusion Decommissioned 13-Dec-2019

Rag Status: 

GREEN

Report by Ken Miller for August 2019

Achievements this period

  • Project Brief raised and approved.
  • Assist with the production and sign off of DPIA which has been forwarded to the Data Protection team for review.
  • Production of initial EqIA.  Forwarded to the Information Services, Disability Information Officer for review and approval
  • Engage with Procurement regarding process to purchase preferred solution.
  • Engagement with Fivium regarding case migration process to the replacement eCase.

Issues

  • Slight delay in procurement process is delaying fully engaging with Fivium in the technical aspects of the transition process.

Next steps

  • Project Brief raised and approved.
  • Sign off of DPIA and EqIA.
  • Engage with Procurement regarding process to purchase preferred solution.
  • Continued engagement with Fivium regarding various aspects of transition process.

 

STU266 - UG & PG Degree Finder Options Appraisal

Category:  Discretionary

Milestones

Milestone Due Date
Planning 20-Sep-2019
Delivery (Options Appraisal) 08-Nov-2019
Closure 22-Nov-2019

Rag Status: 

GREEN

 

Report by Ben Armstrong for August 2019

Achievements this period

  • Project approved to start by IS and CAM

Issues

  • None noted

Next steps

  • Complete project planning stage

CLOSED Projects

 

STU252 - Worktribe BI Suite Universe - Research Management BI MI Enhancements

Category: Discretionary

RAG Status

BLUE (Closed) 

Report by Jamie Thin 

STU253 - PGR Opportunity Finder

Category: Discretionary

RAG Status

BLUE (Closed)

Report by Geoff Cropley 

 

 

STU258 - Careers - Student Alumni Community Networking Platform

Category : Discretionary

RAG Status

BLUE (Closed)

Report by Richard Bailey 

 

STU263 - Options Appraisal for Replacement of INFORMATION REQUEST PLANNING MONITORING TOOL 

Category:  Compliance

BLUE (Closed)

Report by Ken Miller

STU264 - CAM UG & PG Degree Finders Small Enhancements

Category: Discretionary

RAG Status

BLUE (Closed)

 

Report by Chris Konczak

Programme Info

Not available.

Documentation

Not available.