- Report Date
- August 2019
Achievements in Last Period
- Inventory of data centre switches created, updated and cleansed
Risks/Issues
- Work on project scope and planning not started
Next Steps
- Define scope, requirements and timeline
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days