Report for August 2019

Report Date
August 2019

Report for July 2019

Report Date
July 2019

During August 

  • The planning for the new project ACS042 - Delivered Catering Procurement has commenced 
  • The programme budget at the start of the year has been set at 130 days 
Programme Management 10 days
Delivered Catering Procurement 50 days
Delivered Catering Procurement Implementation 50 days
Sponsor Funded Contingency 20 days
Total 130 days

Forward Look 

Resource Position 

 

Section Two: Projects Not Started

 

There are no  further scheduled projects for 2018-19

 

Project Info Programme Managers Commentary

 

AP90-005

 

 

Delivered Catering Implementation

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

ACS042

Delivered Catering Procurement 

Category: Discretionary

Sponsor Funded 

Milestones

Milestone Date Due
Planning 20/09/19

 

Achievements This Period

  • Project initiated 
  • First draft of project brief completed and circulated to the business

Issues

  • None

Next Steps

  • Complete planning phase confirming 
    • project brief
    • project plan 
    • project estimate 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

 

Section Five: Programme Risks

Date Updated Risk Ref. Programme Risks RAG Status Risk Owner
10/09/19 9 Programme Management budget for 2019-20 being exceeded Green Andrew Stewart
02/07/19 10 Completion of Programme Activity within 2019-20 Green Claire Barnish

Section Six : Programme Meeting Minutes

The minutes from the programme meetings since July 2018 can be located on the Accommodation Catering and Events SharePoint site

 

AttachmentSize
Image icon 201907_resources.png24.38 KB
Image icon 201907a_rag.png25.49 KB

Programme Info

Not available.

Documentation

Not available.