Report for August 2019
- Report Date
- August 2019
Report for July 2019
- Report Date
- July 2019
During August
- The planning for the new project ACS042 - Delivered Catering Procurement has commenced
- The programme budget at the start of the year has been set at 130 days
| Programme Management | 10 days |
| Delivered Catering Procurement | 50 days |
| Delivered Catering Procurement Implementation | 50 days |
| Sponsor Funded Contingency | 20 days |
| Total | 130 days |
Forward Look


Resource Position


Section Two: Projects Not Started
There are no further scheduled projects for 2018-19
| Project Info | Programme Managers Commentary |
|
AP90-005
|
Delivered Catering Implementation |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||
|
Delivered Catering Procurement Category: Discretionary Sponsor Funded Milestones
|
Achievements This Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
Section Five: Programme Risks
| Date Updated | Risk Ref. | Programme Risks | RAG Status | Risk Owner |
| 10/09/19 | 9 | Programme Management budget for 2019-20 being exceeded | Green | Andrew Stewart |
| 02/07/19 | 10 | Completion of Programme Activity within 2019-20 | Green | Claire Barnish |
Section Six : Programme Meeting Minutes
The minutes from the programme meetings since July 2018 can be located on the Accommodation Catering and Events SharePoint site