Report for August 2019

Report Date
August 2019

Achievements

  • Project put live.
  • Closure report written.
  • Project closed.

Issues

  • None. 

Next Steps

  • None.
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
42.0 days
Activity this month
6.5 days
Activity this year
35.0 days
Activity to date
35.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days