Report for July 2019

Report Date
July 2019

Achievements this Period

  • A demonstration was provided by the University of Manchester on their product.
  • A Recommendations Paper has been written and shared with project team members.
  • This has been discussed with project team members and conversation recorded for the benefit of one sponsor unable to attend. 

Issues

  • None.  

Next Steps

  • To reach a decision on the way forward.
  • To bring project closure.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Change Commentary
Project is progressing to plan.
Activity
Approved budget
42.0 days
Activity this month
4.5 days
Activity this year
28.5 days
Activity to date
28.5 days
Estimate to complete current year
0.0 days
Estimate to complete future years
1.5 days