Report for June 2019

Report Date
June 2019

Resource Position

 

Forward Look

 

 

 

 

Section 2: Projects Not Started

Project Info

Programme Managers Commentary

N/A

N/A

 

 

Section 3: Projects in Progress

 

Project Info

Project Managers Commentary

 

FIN119 (AP67-024)

eInvoicing

Core Funded

Agreed at WIS - 26-Apr-2019, these will need reviewing again in light of continued bug fixes / acceptance testing:

Target Date Title  
03-May-2019   Development & Deployment of the API / XML Handler  
28-May-2019 On-board the First 3 Suppliers  
25-Jun-2019 On-board the Second 5 Suppliers  
05-Jul-2019 Phase 2 – Deployment sign off  
12-Jul-2019 Project closure  

 

RAG Status : RED

 

Report By Richard Bailey for June 2019

For reference:  SG = Scottish Government,  SGS = Scottish Government Solution

Achievements this Period

  • The Project remains escalated to the Senior Supplier and Head of Development Services
  • Acceptance testing has continued and at the point of writing this report the 'show stopping' bugs that had been identified at that time were addressed and were back with Finance for testing / sign off, however an issue has seen the application stop working again (see Issues below)
  • A draft proposal to complete the project has been proposed which takes the Project into the 2019/20 financial year, which once agreed will see the Project milestones reset and its status should be able to reduce back to Amber
  • FIN119 continues to work closely and successfully with MLE005 for Developer Resource

 

Issues

 

Next Steps

  • Resolve the current issue with the eInvoicing application to allow the completion of acceptance testing, working closely with MLE005 and the Resource Manager to maintain Developer access
  • Look to gaian agreement against the Project Proposal, to define revised milestones and agree a new date to Go live, in coordination with the SG
  • PICCL milestones / change once acceptance testing is completed / the dates are agreed 
  • Deploy / go live with the first Supplier (XMA Ltd) 
  • Agree date to on-board further Suppliers

 

FIN125

Media Production for Annual Report and Accounts                                              

Sponsor Funded

Milestones

  Milestone Due Date
  Closure Review 31-Jul-2019

 

RAG Status: GREEN

Report By Tim Gray for June 2019

Issues

  • None

Next Steps

  • No more production planned for 2018/19.
  • Make decision, whether to close this project or add days for content production

FIN126

Core Funded

Essential Finance System Compliance Updates and Document Revitalisation

 

Milestones:

Proposed milestones are:

Stage Milestone Due Date Complete   
Plan

 (A) Signed Letter of engagement

20-March-2019  Yes
Plan  Planning Complete (Project Brief) 03-May-2019  Yes
Analyse     (B) Business Analysis Complete          07-June-2019  Yes
Execute  (A) Completion of For:sight Proof of Concept phase 14-June-2019  No
Analyse  Re-Planning Post Compliance (Phase (B)) Scoping 14-June-2019  No
Build  (B) Build Complete 28-June-2019  No
Accept  (B) Acceptance Testing Complete 05-July-2019  No
Deliver  (A) Purchase of Arkk, For:sight bridging software 19-July-2019  No
Deliver  (B) Deploy to Live 19-July-2019  No
Close  Project Closure 02-Aug-2019  No

 

RAG Status: AMBER

Report By Ken Miller for June 2019

 

Achievements in Last Period

  • Completed POC instance completed in prep for MTD UAT.
  • MTD UAT delayed due to Intrastat deadline at Finance.  UAT is now underway.
  • On-going work between Finance and Arkk to confirm all input file structures are acceptable to the PoC environment.
  • DPIA requirements raised with the Data Protection Officer (DPO).
  • Work stream (B) completed initial requirements capture and analysis.
  • Meetings held with Finance to confirm present position regarding both project work streams.

Issues

  • It has been reported that we may require a new legal contact.  This needs confirmed so that impact on the project can be minimised.
  • Work stream (B) requires milestones updated to reflect revised schedule.

Next Steps

Work Stream (A)

  • Complete and sign off UAT.
  • Dual run of For:sight output against present process to be undertaken for the last quarter.
  • DPIA to be addressed once UAT has been signed off.

Work Stream (B)

  • Completion of analysis of requirements capture.
  • Forward requirements on to Advanced for their review.
  • Set up TestRail for initial "As is" and post development UAT.
  • Advanced consultant on site 17/18 July to carry out development work. 

 

FIN127

Finance General Data Protection Regulation (GDPR)

Core Funded

Milestones

Milestone Due Date Complete  
Planning 01-Feb-2019  Yes
Analysis 03-May-2019  No
Solution Options 07-Jun-2019  No
Implementation Plan 28-Jun-2019  No
Delivery 30-Sep-2019  No
Closure 28-Oct-2019  No

 

RAG Status : AMBER

 

Report By Ken Miller for June 2019

 

Achievements in Last Period

  • Review of Finance artefacts  completed with regards identification of GDPR data.
  • Internal review of 2018/19 timescales freed contingency for use by FIN119

Issues

  • Simone Martin has been identified within Finance to backfill for John Bannaghan.
  • In response to the re-planning meeting it is expected that project milestones will require re-estimating.

Next Steps

  • Confirm scope of implementation of GDPR patch.

  • Completion of GDPR compliance analysis phase.

  • Re-planning meeting  based upon GDPR compliance analysis results to confirm revised schedule and scope of project to be carried into 2019/20.

 

FIN128

FPM Upgrade

Core Funded

Milestones

Milestone Due Date
Planning 01-03-2019
Delivery 26-07-2019
Closure 01-08-2019

 

 RAG Status : AMBER

Report By Leon Toland for June 2019

Achievements in Last Period:

  • Release and deployment of FPM v2.4.0.17 in Dev
  • Initial Finance-team UAT testing activities in Dev environment
  • Deployment of FPM v2.4.0.17 in Test environment
  • Dev Technology team assessment of resolution level of FPM penetration testing issues (found during FIN118) in Dev environment.

Issues:

  • Potential availability of sufficient Finance UAT resources to support FPM acceptance testing (in Test), whilst FIN119 is the FIN programme priority in 18/19

Next Steps:

  • Finance-team UAT testing activities in Test environment
  • Production deployment of FPM v2.4.0.17 and Paperclip v4.0.1.12

 

FIN129 - PCI DSS Audit

Core Funded

 Project Initiation Complete 22/04/19
 Project Planning Complete 07/06/19
 Workshop 1 - Scope Complete 27/05/19

 Workshop 2 - Actions Complete

12/06/19

 Workshop 3 - Options Complete

27/06/19

 Workshop 4 - Recommendations   

10/07/19
Project Delivery Sign-off

26/07/19

Project DSOR Sign-off

02/08/19

 

 RAG Status : GREEN

Report By Kevin Hone for June 2019

Achievements in Last Period:

  • A further workshop was held to review collated details to date.
  • A Wiki page for the Card Payment Gateway has been created and begun to be populated with technical information.
  • Questions relating to the Card Payment Gateway have now been answered.

Issues:

  • None.

Next Steps:

  • A meeting is to be arranged with the ITI Communications and Infrastructure Section Manager (David Graham) to conclude work on VOIP and to seek answers to the corresponding audit questions.
  • The Wiki page is to be completed with further information and detail on the answered Payment Gateway questions.
  • Questions relating to the Security Policy are to be shared/discussed with Alistair Fenemore for population.
  • Closure of project with future recommendations to be documented, where necessary.

 

 

 

 

Section 4: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

FIN118 (AP56-016)

eFinancials upgrade

 

Closure Report

FIN123 (AP56-016)

Annual Finance Document Revitalisation 17/18

Closure Report

 

AttachmentSize
Image icon 201906-resources.png31.42 KB
Image icon 201906-rag.png59.16 KB