Project Info
|
Project Managers Commentary
|
FIN119 (AP67-024)
eInvoicing
Core Funded
Agreed at WIS - 26-Apr-2019, these will need reviewing again in light of continued bug fixes / acceptance testing:
RAG Status : RED
|
Report By Richard Bailey for June 2019
For reference: SG = Scottish Government, SGS = Scottish Government Solution
Achievements this Period
- The Project remains escalated to the Senior Supplier and Head of Development Services
- Acceptance testing has continued and at the point of writing this report the 'show stopping' bugs that had been identified at that time were addressed and were back with Finance for testing / sign off, however an issue has seen the application stop working again (see Issues below)
- A draft proposal to complete the project has been proposed which takes the Project into the 2019/20 financial year, which once agreed will see the Project milestones reset and its status should be able to reduce back to Amber
- FIN119 continues to work closely and successfully with MLE005 for Developer Resource
Issues
Next Steps
- Resolve the current issue with the eInvoicing application to allow the completion of acceptance testing, working closely with MLE005 and the Resource Manager to maintain Developer access
- Look to gaian agreement against the Project Proposal, to define revised milestones and agree a new date to Go live, in coordination with the SG
- PICCL milestones / change once acceptance testing is completed / the dates are agreed
- Deploy / go live with the first Supplier (XMA Ltd)
- Agree date to on-board further Suppliers
|
FIN125
Media Production for Annual Report and Accounts
Sponsor Funded
Milestones
RAG Status: GREEN
|
Report By Tim Gray for June 2019
- Filming and post-production for SRS lecture completed
Issues
Next Steps
- No more production planned for 2018/19.
- Make decision, whether to close this project or add days for content production
|
FIN126
Core Funded
Essential Finance System Compliance Updates and Document Revitalisation
Milestones:
Proposed milestones are:
Stage |
Milestone |
Due Date |
Complete |
Plan |
(A) Signed Letter of engagement
|
20-March-2019 |
Yes |
Plan |
Planning Complete (Project Brief) |
03-May-2019 |
Yes |
Analyse |
(B) Business Analysis Complete |
07-June-2019 |
Yes |
Execute |
(A) Completion of For:sight Proof of Concept phase |
14-June-2019 |
No |
Analyse |
Re-Planning Post Compliance (Phase (B)) Scoping |
14-June-2019 |
No |
Build |
(B) Build Complete |
28-June-2019 |
No |
Accept |
(B) Acceptance Testing Complete |
05-July-2019 |
No |
Deliver |
(A) Purchase of Arkk, For:sight bridging software |
19-July-2019 |
No |
Deliver |
(B) Deploy to Live |
19-July-2019 |
No |
Close |
Project Closure |
02-Aug-2019 |
No |
RAG Status: AMBER
|
Report By Ken Miller for June 2019
Achievements in Last Period
- Completed POC instance completed in prep for MTD UAT.
- MTD UAT delayed due to Intrastat deadline at Finance. UAT is now underway.
- On-going work between Finance and Arkk to confirm all input file structures are acceptable to the PoC environment.
- DPIA requirements raised with the Data Protection Officer (DPO).
- Work stream (B) completed initial requirements capture and analysis.
- Meetings held with Finance to confirm present position regarding both project work streams.
Issues
- It has been reported that we may require a new legal contact. This needs confirmed so that impact on the project can be minimised.
- Work stream (B) requires milestones updated to reflect revised schedule.
Next Steps
Work Stream (A)
- Complete and sign off UAT.
- Dual run of For:sight output against present process to be undertaken for the last quarter.
- DPIA to be addressed once UAT has been signed off.
Work Stream (B)
- Completion of analysis of requirements capture.
- Forward requirements on to Advanced for their review.
- Set up TestRail for initial "As is" and post development UAT.
- Advanced consultant on site 17/18 July to carry out development work.
|
FIN127
Finance General Data Protection Regulation (GDPR)
Core Funded
Milestones
RAG Status : AMBER
|
Report By Ken Miller for June 2019
Achievements in Last Period
- Review of Finance artefacts completed with regards identification of GDPR data.
- Internal review of 2018/19 timescales freed contingency for use by FIN119
Issues
- Simone Martin has been identified within Finance to backfill for John Bannaghan.
- In response to the re-planning meeting it is expected that project milestones will require re-estimating.
Next Steps
-
Confirm scope of implementation of GDPR patch.
-
Completion of GDPR compliance analysis phase.
-
Re-planning meeting based upon GDPR compliance analysis results to confirm revised schedule and scope of project to be carried into 2019/20.
|
FIN128
FPM Upgrade
Core Funded
Milestones
RAG Status : AMBER
|
Report By Leon Toland for June 2019
Achievements in Last Period:
- Release and deployment of FPM v2.4.0.17 in Dev
- Initial Finance-team UAT testing activities in Dev environment
- Deployment of FPM v2.4.0.17 in Test environment
- Dev Technology team assessment of resolution level of FPM penetration testing issues (found during FIN118) in Dev environment.
Issues:
- Potential availability of sufficient Finance UAT resources to support FPM acceptance testing (in Test), whilst FIN119 is the FIN programme priority in 18/19
Next Steps:
- Finance-team UAT testing activities in Test environment
- Production deployment of FPM v2.4.0.17 and Paperclip v4.0.1.12
|
FIN129 - PCI DSS Audit
Core Funded
Project Initiation Complete |
22/04/19 |
Project Planning Complete |
07/06/19 |
Workshop 1 - Scope Complete |
27/05/19 |
Workshop 2 - Actions Complete
|
12/06/19
|
Workshop 3 - Options Complete
|
27/06/19
|
Workshop 4 - Recommendations
|
10/07/19 |
Project Delivery Sign-off |
26/07/19
|
Project DSOR Sign-off |
02/08/19
|
RAG Status : GREEN
|
Report By Kevin Hone for June 2019
Achievements in Last Period:
- A further workshop was held to review collated details to date.
- A Wiki page for the Card Payment Gateway has been created and begun to be populated with technical information.
- Questions relating to the Card Payment Gateway have now been answered.
Issues:
Next Steps:
- A meeting is to be arranged with the ITI Communications and Infrastructure Section Manager (David Graham) to conclude work on VOIP and to seek answers to the corresponding audit questions.
- The Wiki page is to be completed with further information and detail on the answered Payment Gateway questions.
- Questions relating to the Security Policy are to be shared/discussed with Alistair Fenemore for population.
- Closure of project with future recommendations to be documented, where necessary.
|