- Report Date
- June 2019
Achievements this period
- First combined meeting for Embargo & Clearing with all Stakeholders took place in order to discuss further steps
- Development of the SharePoint Site was inititiated
- All Meetings within the Clearing Period are set up
- Project Brief was signed off
Issues
- SharePoint Development might primarily be conductible in June due to the limited availability of the resources from July onwards
Next Steps
- Further clarification and finalisation of the required SharePoint Development required
- Project Services Intern to start SharePoint training to potentially be able to cover
- Approved budget
- 50.0 days
- Activity this month
- 3.8 days
- Activity this year
- 13.8 days
- Activity to date
- 13.8 days
- Estimate to complete current year
- 14.0 days
- Estimate to complete future years
- 26.0 days