WIS gave approval to closing the Project Planned Milestone.
The overall project is progressing to plan.
Requirements have now been gathered and are in a state for co-sponsor review. A meeting is scheduled to completed this task.
Engagement has been had with resource from Command both in the UK and with a support manager in Poland.
Engagement has been had with procurement awaiting feedback on intended Prior Information Notice (PIN) and steps involved in Public Contracts Scotland (PCS).
Issues
The Business Analyst being on annual leave at project start-up meant that in order to advance initial activities, the Project Manager took on the role for a period.
It has been difficult to engage with resource from the Medical under-graduate course due to non-availability.
Next Steps
To sign-off business requirements (to be presented in the form of a mind-map).
To issue a PIN with questions for respondents to complete.
To seek a wider audience of potential suppliers.
To organise product demonstrations.
To populate an options paper with recommendations.