Report for May 2019

Report Date
May 2019

Achievements in Last Period

  • agreed with Matt a date to present dates to PMS
  • closed project  

Issues and Risks

  • none

Next Steps

  • none

Future Milestones

n/a

 

Budget

The budget for this project has been fully used.

 

iti031_university_calendar_-_budget.xlsx

 

Project Sponsor Commentary

None.

 

 

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Change Commentary
the service documentation will be reviewed. changed and finalised over Dec/Jan
Activity
Approved budget
18.5 days
Activity this month
5.0 days
Activity this year
18.0 days
Activity to date
18.0 days
Estimate to complete current year
0.1 days
Estimate to complete future years
0.0 days