Update to 29 March 2019
- Report Date
- March 2019
Achievements in last period
Project
- Project team recruited (Milestone completed)
- Academic Lead recruited
- Project Scope and Phase 1 completion milestones updated to 12 April to match 1st meeting of Design Group
- Risk and Issue logs updated
- Project plan updated
Current Workstream - Current State Assessment (CSA)
- Field trip criteria defined (subject to Design Group review)
- Student engagement plan defined
- Design principles agreed
- CSA scope/structure agreed
- Schools engagement plan agreed
Risks and issues for escalation
- Review and Consultation - Student Availability - Student engagement difficult. Surveys team don't recommed surveys for most students due to low response rates and open-ended questions. Workshops hard to schedule with low engagement, clashes with holidays and exams. Intention to carry out restricted surveys (OLL and alumni) with pop-up sessions in social areas to get wide range of students
Risk Log - unpublished/project/sas017/risks
Upcoming Activities
Project
- Design Group - Review/approval of PID, Field trip approach, student engagement approach, schools engagement approach
- Design Group - Design principles review
Current Workstream - Current State Assessment (CSA)
-
Issue Alumni and OLL survey
- UK institutes site visits
- School engagement sessions
- Student pop-up sessions
- Ongoing literature review
- Conference attendance
Milestones
| Stage | Milestone | Due Date | Complete |
|---|---|---|---|
| Initiate | Project Team Recruited | 11-Mar-2019 | Yes |
| Plan | Project Scope, Governance, Design Group membership and ToR signed-off | 12-Apr-2019 | No |
| Plan | Phase 1 Completion Approval - Planning Completed | 12-Apr-2019 | No |
| Execute | Current State Assessment (CSA) finalised | 24-May-2019 | No |
| Execute | Phase 2 Completion Approval - CSA Completed | 24-May-2019 | No |
| Execute | Options Appraisal Consultation version drafted | 12-Jul-2019 | No |
| Execute | Options Appraisal finalised | 06-Sep-2019 | No |
| Execute | Phase 3 Completion Approval | 27-Sep-2019 | No |
| Close | Project Closure | 11-Oct-2019 | No |
- Approved budget
- 0.0 days
- Activity this month
- 30.0 days
- Activity this year
- 31.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 90.0 days
- Estimate to complete future years
- 0.0 days