Impact

Priority and Funding

  • Priority 3 (normal)
  • Core

Initial Cost Estimates

Exact external costing will depend upon the product purchased and any specific configuration work required.  Of the 3 solutions under investigation at present the most expensive quote provided is:

External spend :

Cost Element 2019/20 2020/21 2021/22 2022/23
Software licence costs (Inc Vat) £12,600 £12,600 £12,600 £12,600
Other supplier costs (Inc Vat) £17,600      
Total £30,200 £12,600 £12,600 £12,600

The solution is being purchased as a SaaS (Software as a Service) via the G-Cloud 11 framework on the Digital Marketplace.  The application will be hosted remotely rather than on site.  As a result it is expected that post implementation support costs will be kept to a minimum.  As part of the service initiation an OLA will be required between Records Management and Production Management.  This will cover the on-going internal support of the project along with any related internal support costs.

Impact and Dependencies

  • The present version of ColdFusion solution has a technical end of Life as of May 2019.
  • The project effort has been assigned as follows:
    • Financial year 2018/19 - 30 days
    • Financial year 2019/20 - 70 days
  • The procurement of the product will include an element of training for the Records Management team.  There may also be the need for a wider training/communication programme for the various individuals across the University, external to Records Management, who are requested to contribute to FoI responses.  

Project Risks

Ref: Risk Description Initial Risk Current Risk Status Management Approach Risk Owner
1 Product evaluation. Green Green Open Reduce Anne Grzybowski
2 Resource availability - Records Management Green Green Open Reduce Anne Grzybowski
3 Resource availability - IS Green Green Open Reduce Ken Miller
4 Funding only available in 2018/19 Green Green Closed Avoid Ken Miller
5 Change of Procurement contact Green Green Closed Retain Ken Miller
6 No funding available for system purchase Amber Amber Closed Remove Tracey Slaven
7 Days assigned to 2019/20 insufficient Green Green Open Reduce Ken Miller
8

Historic data migration may prove more complicated than estimated for

Amber Amber Open Reduce Ken Miller
9

Availability of Development Services representative

Green Green Open Reduce Bill Lee

Project Info

Not available.

Documentation