February 2019

Report Date
February 2019

Achievements in Last Period

  • completed TRN upgrade
  • completed Test regression testing

Issues

  • n/a

Next Steps​

  • LIVE upgrade week-end 8th March

Milestones

Milestones Due Date
Upgrade LIVE 10-Mar-2019
Upgrade Live - Fall Back date TBC 17-Mar-2019
Deployment Sign Off Review (DSOR) 25-Mar-2019
Second refresh of TEST 12-Apr-2019
Clone DUST from Live 17-Apr-2019
Close 03 May 2019
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
200.0 days
Activity this month
46.0 days
Activity this year
141.0 days
Activity to date
141.0 days
Estimate to complete current year
61.0 days
Estimate to complete future years
0.0 days