Report for February 2019

Report Date
February 2019

Achievements

  •  PICCL raised to progress withdrawal

Issues

  • n/a

Next Steps

  • Withdrawal is expected to be submitted to WIS 08/03/19

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation