Report for Jan 2019

Report Date
January 2019

** DRAFT **

Report compiled by  Jamie Thin (IS Apps Programme Manager) 

for Jim McGeorge (USG), Tracey Slaven (GASP) ,Theresa Merrick (CAM) , Niall Bradley (CAM),  Steven Ross (CAM) , Paddy Corscadden (SDS),Gael Campbell (SDS) ,Ronnie Millar( SCS) ,Jane Johnston (SRA), Rebecca Gaukroger(SRA), Ailsa Vamplew (SRA), Lesley Stokes (SRA), Laura Cattell (SRA) , Clare MacKay (SRA) , Shellagh Green (Careers) , Damon Querry (RIS), Rena Gertz (Data Protection Officer), Sara Cranston (Records Management), Karsten Moerman (IAD) , Jon Turner (IAD) , Sarah Macallister (IAD) , Andrew Crossland (Student Systems) , Rena Gertz (GaSP)  and other interested business area owners.

 

Section One: Programme Commentary, RAG and Resources Update

Commentary

 

The STU programme is RED, as one of the projects is RED and 2 others are AMBER

Emerging resource conflicts across IS Apps Software Dev team for both STU264 and STU260 for the UG  & PG Degree Finders enhancements and security strengthening work.

 

Overall the burn-rate of IS Apps spend across the STU projects for 18-19 after first 6 months is 76 %, this may pick up if the follow-on project to replace the FOI request planning monitor tool gets approval to start in Feb 2019.

 

 

Programme Risks ( RED & AMBER)

   

UG & PG Degree finder-Business Continuity Plan to be updated by Dec 2019( STU260 - CAM UG & PG Degree Finders) AMBER             Niall Bradley
Additional compliance work may affect scheduling and budgets of other projects during 2018-19  (STU Programme) AMBER Jim McGeorge
Existing 'Mobility Online' solution will not be decommissioned by SEP SAS0014/ SAS016 Work & Study Away project ( need to be kept for in progress Student exchanges and to continue to support Staff exchanges going forward)  AMBER Jim McGeorge

 

RAG & Forward Look to end of Jan 2019

 STU RAG to end of Jan 2019   

 

 

Resources to end of Jan 2019

 STU actual spend to end of Jan 2019

 

 

 

Section Two: Projects Not Started

 

All currently approved projects are in progress.

There will be a  follow-on project for  Records Management  in 18-19 to implement the recommendations from STU263, subject to outcome of the options appraisal , and availability of sponsor funding and business resources

AP89-034 Implement Information request planning monitor tool (FOI and GDPR compliance) 

AP89-035 Replace information request planning monitor tool (FOI and GDPR compliance) 

153 days effort is set-aside for the IS Apps work to support the implementation of the new system incl project management / business analysis / system integration - as required.

 

Section Three: Projects in Progress

 

Project Info

Project Managers Commentary

STU252 - Worktribe BI Suite Universe - Research Management BI MI Enhancements

Category: Discretionary

Milestones

22-Feb 2019 Withdrawal

RAG Status

YELLOW (Suspended)

Report by Jamie Thin  for Jan 2019

Achievements this period

  • None - project suspended
    • RIS business area are evaluating other BI Tools and reporting options incl Power BI

Issues

  • No new issues

Next steps

  • agree closure / withdrawl report
  • project expected to be withdrawn by end of Jan 

Milestones

Withdrawal - 22-Feb 2019

STU253 - PGR Opportunity Finder

Category: Discretionary

Milestones

Target Datesort descending Previous Date Title Stage Complete
31-Aug-2017  30-Jun-2017 End of Planning Plan Yes
05-Feb-2018 No date available       Unsuspend project and Kick off the development work Execute No
11-May-2018 23-Mar-2018 End of Planning (re-plan following suspension) Plan Yes
25-May-2018 No date available System Design - Research PURE API Design Yes
19-Jun-2018 No date available Build Complete Build Yes
31-Oct-2018 No date available Deployment Deliver Yes
25-Jan-2019 No date available Design Design No
08-Feb-2019 No date available Build Build No
28-Feb-2019 No date available Project Closure Close No

RAG Status

Green

Report by Geoff Cropley for January 2019

Achievements this period

The revised design and proof on concept (POC) using the alternative products has been built. 

Dev Services have been engaged to produce front-end re-design and build.

SEP has been consulted on taking the demonstrator to the next level.  The timing for this is July 2019 when sufficient resources become available

 

Issues

  • None

Next steps

  • Build demonstrator application for hosting in test environment

STU257 Privacy Impact Assessment Tool

Category: Compliance

Milestones

The project will now require to be re-planned in conjunction with the supplier 

Target Date  Title
08-Feb-2019 Contract Award
t.b.c. Complete Application Familiarisation and Setup
t.b.c. Complete User Guides
t.b.c. User Acceptance
t.b.c. Deployment to Live
t.b.c. Deployment Sign-Off
t.b.c. Closure

RAG Status

AMBER

  Report by Andy Stewart for January 2019

 

Achievements

  • Procurement 

    • After further discussions with the supplier, the contract has been agreed, signed by UOE and returned to the supplier for final signature

Issues 

  • Due to the extended period to agree the contract

    •  It has not been possible to progress any further with the project  due the contract not being signed 

Next Steps

  • EQIA - to be completed
  • UoE to get access to cloud based application 
  • Implementation and Training plan to be agreed with supplier 
  • Commence Implementation and training 

 

RAG Commentary
Delays in signing the contract with the supplier has greatly impacted on the project delivery. The contract was finally agreed and signed by UoE on 1st February 2019. Having reached agreement with the contract, the project can now be re-planned and re-estimated. Due to the elongated period to complete the contract negotiations, it is anticipated that additional budget will be required to complete the project

 

STU260 CAM  Degree Finders - Options Appraisal 

Category:  Compliance

Milestones:

01-Feb 2019 End of Planning

RAG Status:

AMBER

 Report by Jamie Thin for Jan 2019

Achievements this period

  • No progress - waiting for Dev work for STU264 to be completed first

  • The work on the security strengthening package is on hold , pending availability of IS Dev services resources after STU264 has been delivered

Issues

  • Dependency on STU264 - the urgent small enhancements to the UG & PG degree finder should be delivered first via STU264, then the security work can be delivered after STU264 goes LIVE
  • Dependency on SEP SAS PCIM analysis & SRA analysis - the future PCIM / SRA Website solution may not provide a complete end-to-end solution for CAM for all marketing data associated to Programmes.  
    • STU260 should attempt to understand the potential size of any gap , so that Service owner (CAM) can make a bid for additional funding / submit business case to SEP for another future project
    • initial response with answers to STU260 questions received from Emma Rowson (SEP), fuller details will be available from Feb 2019 once initial PCIM analysis complete.

Next Steps

  • Get resources booked  to deliver the  security strengthening dev work for both the UG & PG applications
    • initial estimates are that the work is relatively small , so it is recommended that it is delivered as a work package within STU260 rather then spinning up a separate project to do the security work
    • make bookings with the S/W dev team to start after STU264 has gone live

STU263 - Options Appraisal for Replacement of INFORMATION REQUEST PLANNING MONITORING

TOOL 

Category:  Compliance

Milestones

4-June-2018 End of Planning
12-Oct-2018            BRD Document Released for Review
29-Oct-2018 Options Appraisal Signed Off
30-Nov-2018 Analysis of Requirements - Signoff Complete
21-Feb-2019 Options Appraisal Delivered
08-March-2019 Project Closed

Rag Status:

 GREEN

Report by Ken Miller for December 2018

Achievements

  • Initial options appraisal document completed for review.
  • Feedback received and incorporated into the final options paper.

Issues

  • Initial draft appraisal paper wasn't available until early January.  Revised milestones approved at Feb 1st WIS.

Next Steps

  • Revised options appraisal document completed for discussion at options review meeting.
  • Final options paper discussed at review meeting.
  • Options paper signed off and outstanding project actions agreed.

 

 

STU264 CAM UG & PG Degree Finders Small Enhancements

Category - Discretionary

Milestones

Build stage complete in DEV 27-Feb-2019
Deploy to TEST 01-Mar-2019
Apps mgt peer testing in TEST 08-Mar-2019
Build re-work after Integration test and UAT 14-Mar-2019
CAM Complete UAT 18-Mar-2019
Deploy changes to UG Degree finder to LIVE 20-Mar-2019
Deploy changes to PG Degree finder to LIVE 20-Mar-2019
Deployment review sign-off 29-Mar-2019
Project Closure 12-Apr-2019

Rag Status:

RED

Report by Chris Konczak for January 2019

Achievements

  • Development of JIRA 19 and 20 continuing. This has been submitted to CAM for their testing and it has been returned with some minor amendments.

Issues

  • New resource conflict in IS Apps Software Dev team - conflict with TEL Learn to the Cloud project - this puts future STU264 milestones at risk until new resourcing plan can be agreed with the IS Apps Dev resource manager and STU264 can be re-planned 
  • Dates for development and testing milestones will change from knock-on impact of resource conflict for the lead developer 
  • Any new business requirements  could put the project over the existing allocated budget.

Next Steps

  • Test and deploy JIRA 19 and 20.
  • Re-plan the  remaining development of the other JIRAs.
   

CLOSED Projects

 

STU258 - Careers - Student Alumni Community Networking Platform

Category - Discretionary

Milestones

18-Jun-2018 Launch of website
29-Jun-2018 Delivery sign-off
16-Nov-2018   Project closure

RAG Status

BLUE (Closed)

Report by Richard Bailey 

 

 

 

Programme Info

Not available.

Documentation