Report for January 2019
- Report Date
- January 2019
Report compiled by Muriel Mewissen (IS Apps Programme Manager) for Jim McGeorge (USG), Kate Brook (D&A), Jenny Shaw (D&A), Stefan Kaempf (IS Applications), Ian Sutherland (SRA), Jim Galbraith (GaSP) and other interested business area owners.
Section One: Programme Commentary, RAG and Resources Update
Commentary
During January, the only project work took place in planning for USG012 ThankQ Upgrade which is reporting an AMBER RAG status due to the delays in completing planning. USG011 Legal Services SharePoint Site is paused while awaiting development by Service Management on SharePoint planned for 8 March.
The overall USG Other Programme status is GREEN.
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Forward Look - January 2019

Resources to end January 2019
The budget for session 2018/19 is now confirmed as 210 days:
- 106 days for USG portfolio projects
- 104 days for the USG portfolio management
Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
|---|---|
| AP89-930 Clearing 2019 | To be started in March 2019. |
Section Three: Projects in Progress
|
Project Info |
Project Managers Commentary | ||||||||||
|
USG011 Legal Services SharePoint Site
Category: Discretionary
RAG StatusGREEN |
Report by Geoff Cropley for January 2019Achievements
Issues
Next steps
|
||||||||||
|
Category: Discretionary
RAG StatusAMBER |
Report by Chris Konczak for January 2019Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Manager's Commentary |
|---|---|
| USG010 Clearing 2018 | This project was started in March 2018 and was closed on the 21 September 2018. The Completion Report is available to view. |