Monthly Project Report
- Report Date
- January 2019
Achievements
- Draft Brief has been created
- Project website has been set up
- Communication with S2 Unified has confirmed current version
- and latest CalSync version available
Issues
-
No issues
Next Steps
- Complete 3 point estimate for COM048
- Plan COM048 in ASTA
- Revise and complete draft Brief
- Signed off project Brief
- Planning stage complete
GREEN RAG status
Milestones currently in planning
| Milestone | Date |
| Planning - Brief | 15-Feb-2019 |
| Delivery | 04-Jun-2019 |
| Closure | 19-Jul-2019 |
- Approved budget
- 50.0 days
- Activity this month
- 2.0 days
- Activity this year
- 2.0 days
- Activity to date
- 2.0 days
- Estimate to complete current year
- 49.0 days
- Estimate to complete future years
- 0.0 days