Report for November 2018

Report Date
November 2018

Resource Position 

 

 

Forward Look

Section 2: Projects Not Started

Project Info

Programme Managers Commentary

FIN126 - Essential Finance System Compliance Updates and Document Revitalisation

Planning - tbc

Delivery - tbc

 RAG Status : GREEN

Expected to commence in early 2019.

 

 

Section 3: Projects in Progress

 

Project Info

Project Managers Commentary

 

FIN118 (AP56-016)

eFinancials upgrade

Funding: TBC

 

Target Date

Title

26-Oct-2018

Readiness / Approval to Go-Live

12-Nov-2018

Go-Live

30-Nov-2018

Deployment Sign-off

14-Dec-2018

Project Closure

 

RAG Status : GREEN

 

 

 

 

 

 

Report By Lee-Ann Simpson for November 2018

Achievements in Last Period

  • FIN118 successfully deployed to LIVE with all interfaces connected and working.

Issues 

  • eExpenses had to be migrated to an isolated instance post Go-Live due to a 'Java Memory' error messages being received;
  • Various FPM issues experienced in the weeks following Go-Live which resulted in additional support time being spent on the project.
  • Project Manager/ Apps Man and Dev Tech spending significantly more time post Go-Live than anticipated due to the errors being identified by the business.  Most errors were resolved in a timely fashion by the project team.
  • Change of supplier installer occurred on the day of the Go-Live which meant there was an additional risk to the project for the deployment.
  • Change of supplier FPM support potentially impacted on the FPM config/availability post Go-Live due to the new support not being as aware of the UoE requirements for FPM.

Next Steps 

  • DSOR to be signed off (meeting scheduled for 6th December);
  • Lessons learned to be formalised;
  • Decommissioning to be undertaken;
  • Project to be closed

FIN119 (AP67-024)

eInvoicing

Core Funded

Agreed at WIS 12-Oct-2018, as stated in this report these will need to be reviewed again in the very near future:

Target Date Title  
08-Nov-2018 Development & Deployment of the API / XML Handler  
22-Feb-2019 On-board the First 3 Suppliers  
22-Mar-2019 On-board the Second 5 Suppliers  
29-Mar-2019 Phase 2 – Deployment sign off  
12-Apr-2019 Project closure  

 

RAG Status : AMBER

 

Report By Richard Bailey for November 2018

For reference:  SG = Scottish Government,  SGS = Scottish Government Solution

Achievements this Period

  • Development Resource is now re-secured (28-Nov-2018) to continue works against this Project, as expected around 2 weeks of Resource were lost
  • Work again underway to develop the API / XML Handler

Issues

  • None

Next Steps

  • As the Project re-initiates early December the Milestones need to be re-reviewed / realigned to address time lost to other Highest Priority Projects during November (notably FIN118 eFinancials Upgrade and Migration and MLE004 Lecture Room Recordings).  It is not expected that delivery / closure milestones are greatly affected
  • Submit a PICCL to WIS to realign the Project milestones once works / test scheduled are firmed up again
  • Continue work packages / development of the API / XML Handler

FIN123 (AP56-016)

Annual Finance Document Revitalisation 17/18

Core Funded

  Title  
10-Aug-2018  Acceptance Testing v4.1 (ASOR)  
 13-Aug-2018 Deploy/Deliver v4.1 (Major)    
13-Aug-2018 IS Integration v5 Complete  
17-Aug-2018 Acceptance Testing v5 (ASOR)  
20-Aug-2018 Deploy/Deliver v5 (Major)  
31-Aug-2018 Project Closure (Major)  
31-Aug-2018 DSOR (plus deployment checklist)

 

RAG Status : AMBER: Having been red in September, FIN123 has been unable to complete deliverables due to consultant availability to undertake all required work. This impacted the milestones and has resulted in a number of risks and issues to the project which effects stakeholders in Finance (Risk 7(Change to Project Scope) , 8 (Delay to Documentation being Updated), 9(Unable to complete all required changes within allocated time), and Issue 6 (Delay to Milestones)). The Project Team has however now agreed a reduction in scope (moving outstanding compliance requirements from this 2017/18 project into 2018/19 annual project) and a route to closure for this project. This will be undertaken to ensure alignment with dependant project, FIN118. FIN123 will remain as AMBER for November due to the delay in completing the project as a result of the FIN118 deployment and subsequent work undertaken to stabilise the FPM application. As a result, there was no available resource to progress with the outstanding actions to allow FIN123 to be completed.

Above milestone dates will change once these have been approved via WIS on 07/12/2018.

 

 

 

 

 

 

 

Report By Lee-Ann Simpson for November 2018

Achievements

Due to FIN118 deploying mid November, no additional work was undertaken on FIN123 as the remaining work required was dependant on FIN118 being successfully deployed.

Issues 

 

No issues as delay due to FIN118 deployment.

Next Steps 

  • Approval from WIS of change to scope/milestones due to delay received from contractor;
  • User Acceptance Testing to be undertaken in v5 once completed;
  • All remaining changes to implement into Live once acceptance has been completed and signed off.
  • Closure report to be completed;
  • Project to be closed.

FIN125

Media Production for Annual Report and Accounts                                              

Sponsor Funded

Milestones

  Milestone Due Date
  Filming complete 09-Nov-2018
  Post-production complete 30-Nov-2018
  Deliver Media 03-Dec-2018
  Closure Review 21-Dec-2018

 

RAG Status: GREEN

 

 

 

Report By Tim Gray for November 2018

Achievements in Last Period

  • Filming completed on 5th, 6th, and 13th November
  • Post-production almost complete
  • Initial feedback received from key stakeholders has been very positive
  • A total of 6 videos will now be produced

Issues

  • None

Next Steps

  • Complete final stages of post-production
  • Create sub-titles for key videos
  • Close project

 

FIN127

Finance General Data Protection Regulation (GDPR)

Core Funded

Milestones

Milestone Due Date
Planning 30-Nov-2018
Delivery 24-May-2019
Closure 21-Jun-2019

 

 RAG Status : AMBER

Report by Ben Armstrong for November 2018

Achievements

  • DPIA completed in DPIA workshop with Finance team and Data Protection Officer
  • Drafted project brief and high level plan
  • Viewed demo of suppliers' GDPR patch for eFinancials

Issues

  • No agreement yet on project estimate - to be agreed with sponsor and team - cost RAG marked as AMBER
  • GDPR patch for eFinancials not fit for purpose, as it stands - feedback has been provided with supplier and awaiting confirmation - scope RAG marked as AMBER
  • Further time required to complete Planning due to reflection time on DPIA to feed into the project brief and plan - to be incorporated - time RAG marked as AMBER

Next Steps

  • Confirm quality of GDPR patch for eFinancials with Finance and supplier

  • Sign off project brief, plan and estimate to confirm and sign off end of planning stage

Section 4: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

 

 