(Draft) TEL Programme Report compiled by Colin Watt, (IS Apps Programme Manager) for Programme Owner Anne-Marie Scott
Section One: Programme Commentary, RAG and Resources Update
Projects in Progress:
TEL031 VLE Student Analytics
TEL050 Academic Blogging Service
TEL052 QMP Upgrade
TEL057 Learn Foundations
TEL058 Learn to the Cloud
Forward Look and RAG




Resource Summary



Section Two: Projects Not Started
| Project Info |
Project Manager's Commentary |
| AP89-030 Moodle Upgrade |
|
| AP89-031 Learn Upgrade |
|
| AP89-915 TEL Improvements |
Confirmed in TEL Project meeting 06/11/18 that not required this session. |
Section Three: Projects in Progress
| Project Info |
Project Manager's Commentary |
|
TEL031
VLE Student Analytics
Discretionary
Milestones
RAG Status: BLUE
|
Project currently suspended
Project to close
|
|
TEL050
Academic Blogging Service
Discretionary
Milestones
| UAT Complete - Acceptance - Phase 2 (to be reviewed) |
15-Jan-2019 |
| Deployment to Live - Phase 2 (to be reviewed) |
31-Jan-2019 |
| Deployment Review - Phase 2 (to be reviewed) |
08-Feb-2019 |
|
Project Closure
(to be reviewed)
|
15-Feb-2019 |
RAG Status:
AMBER
|
Report by Sonali Nakhate for November 2018
Achievements in Last Period
- Phase 2 Sprint 1 was made live - new plugins, themes and bug fixes.
- Phase 2 Sprint 2 development work in progress.
- Phase 2 - Blogs Archive & Deletion development and policy work in progress.
- Changes to Website Search - new 'Blogs' tab - development and testing complete.
Issues
Next Steps
- Phase 2 sprint 2 to go live.
- Changes to Website Search - new 'Blogs' tab to go live.
- Continue Blogs Archive & Deletion development work.
- Finalise first draft of Blogs Archive and Deletion Policy
- Continue search investigation with Funnelback
- RAG Commentary
- No change from last reporting period. Phase two of the project includes bespoke development work such as change to WordPress search engine, blogs archiving and deletion etc. There is some uncertainty on how the search requirements can be technically met and hence there is medium confidence in Phase 2 being completed in time. So the RAG status of Amber has been selected for Phase 2 of the project in this reporting period.
|
|
TEL052
QMP Upgrade (17/18)
Compliance
Milestones
RAG Status: AMBER
|
Report by Sue Woodger for November 2018
Achievements in Last Period
- Budget reviewed and approved as 88d (was 63d) – wis approval 9/11/18
- LTW confirmed Live deployment date to be wb 7/1/ 18
- Revised milestones agreed and updated – wis approval 9/11/18
- QMP completed Test install and migrations and UAT commenced 7/11/18
- Call submitted to ITI for Live configuration
Issues
- UAT not yet signed off ads there are still issues with managed access and load balancer settings
Next Steps
- LTW to complete testing
- TEST signoff
- LTW documentation tasks to start when TEST signed off
- Live infrastructure to be completed
Rag commentary:
As indicted last month once verified by QMP that TEST is fully upgraded and migrations are complete we can move the project to AMBER. We now have a Test system and it is in UAT so we can move the project to AMBER. There are issues in UAT to do with managed access and load balancer firewall rules and these are being investigated by QMP with support from DevTech and ITI.
Work has started on the LIVE configuration as ITI do not have the resource to wait until UAT is signed but are doing so with the caveat that some rework may be required
|
|
TEL057
Learn Foundations
Discretionary
Milestones
RAG Status: AMBER
|
Report by Laura Woods-Dunlop for November 2018
Achievements in Last Period
- Project plan finalised & activities prioritised
- Design underway - user experience activity supporting design
- Engagement strategy developed
- Student UX activity playbacks complete
- Decision on rollover date for Learn made
- Support from LTC Senate secured
- Project priority moved to highest
- Dependencies on Learn to the Cloud identified
- Communications plan signed off at Project Board
- Festival of Creative Learning planned & submission entered
- Abstract approved by LTW for application to present at Durham Blackboard User Conference
- Piloting opportunities identified
Issues
- No current issues however decision made to re-plan automation workstream due to resource constraints
Next Steps
- Submission for Learning & Teaching Conference
- Sign off engagement strategy & begin implementation
- Sign off evaluation activities with board
- Continue design work for templates & terminology - launch staff & student surveys to identify top tasks and student mental model of categorising tasks
- Presentation to LISC
- RAG Commentary
- AMBER - discussions between LTW and Apps are ongoing about assigning a replacement PM however nothing secured yet.
- In addition resource from DLAM has constraints due to loss of resource within the team putting additional pressure on key
- resource for the project. Re-plan has taken place to alleviate this pressure. Path to GREEN, replacement PM resource needs to be secured. Expected that DLAM resource issue will be addressed through re-plan so no further steps necessary.
|
|
TEL058
Learn to the Cloud
Discretionary
Milestones:
| Complete R&D phase |
31-Jan-2019 |
| Deployment to Live |
08-July-2019 |
| Deployment Review |
22-July-2019 |
|
Project Closure
|
08-Aug-2019 |
RAG Status:
AMBER
|
Report by Sonali Nakhate for November 2018
Achievements in Last Period
- Project planning in progress.
- Scope of R&D phase of the project agreed.
- Project Brief completed and in review by the team.
- Contract paperwork started with Blackboard
Issues
Next Steps
- Project Brief to be signed off by WIS.
- Start R&D stage of the project.
- Sign off contract paperwork
- Blackboard start build of Test SaaS environment.
RAG Commentary
Contract for PM on the project is due to end beginning of January and the paperwork for contract extension has not been completed. Hence the project status has been moved to Amber. Path to Green - Pursue contract paperwork and get it in place before Christmas break.
|
Section Four: Closed or Withdrawn Projects
| Project Info |
Project Managers Commentary |
|
TEL049
VLE Standards
|
Withdrawal Approved 24/07/18 |