w/c 15th October

  • UAT
    • The final two JIRA's (35 and 52) have been closed
    • UAT for phase 1 has been completed
  • Outstanding JIRA's
    • review of remaining 7 JIRA's
  • Project Plan updated to take into account
    • dates for Phase 2
    • re-scheduled activity relating 
      • SDD and security checks
      • data download based on guestimate approval date for DWP
      • OLA and Deployment check lists
      • database views
  • Updated ASTA to reflect above changes, currently projecting 3 days over budget
  • Reviewed project risk register
  • Weekly project team conference call held