Currently little progress regarding testing due to technical issues. Currently awaiting Ingeus to investigate
Ingues have advised that development resource will now be made available between 4th and 9th October, however there is no offer of contingency if the testing cannot be completed in the time period
The issue has been escalated to both the Project Sponsor and Senior Supplier
At the end of the week
4 JIRA's have been closed
14 JIRA's remain outstanding
Weekly teleconference held to
Review Ingeus solution not that UOE job search functionality has been switched back-on. Paul Muller confirmed no change and was as before
Discussion regarding UAT
agreed to progress UAT
further progress review on Monday with request to Ingeus to have alternative resource plan in place to support UAT extending over the period 9th October
Outstanding Activity details have been published on 04/10/18 and will be updated and circulated at the end of each day
Project risk log updated
DWP
Currently waiting for DWP to forward license agreement to the Project Sponsor