Programme Report for September 2018

Report Date
September 2018

Completed by Morna Findlay (IS Apps Programme Manager) for Susan McLaren  (Programme Owner)

 

Section One: Programme Commentary, RAG and Resources Update

 

Commentary

The programme manager considers that overall the programme is GREEN, as the risks associated with the need to upgrade the Erecruitment  application are likely to be downgraded soon.  It is expected that a new contract will be signed in October and that there will be no need to upgrade Erecruitment in 2018/19 or 2019/20.

The start of year budget has been set at 232 days, which contains 20 days of contingency.

 

RED and AMBER Programme Risks

Browser changes may impact erecruitment users AMBER    Stefan Kaempf
Planned Payroll upgrade of Oracle may impact HR propgramme of work     AMBER     Susan McLaren

 

 

Forward Look for September  2018

 

     

 

Resources to end September  2018

 

     

 

Section Two: Projects Not Started

HESA Staff Return 18/19 - expected to start in Spring 2019

 

Section Three: Projects in Progress

Project Info

Project Managers Commentary

HRS094 HESA Staff Return 17/18

Date Milestone
12-Oct-2018 Commit
09-Nov-2018 Final Submission
07-Dec-2018 Closure

RAG Status

GREEN

Project Report by Anne Mathison for September 2018

Achievements

  • HR 'Submit HESA return' milestone was completed early for the September Milestone
  • IS were available to provide support, but were not needed in September

Issues

  • No issues

Next Steps

  • Any HR issues raised to be sorted
  • Any IS issues raised to be sorted
  • HR continue testing and correcting data if required
  • HR will 'Commit' HESA return by 12th October milestone

 

GREEN RAG status

   

HRS096 GDPR Updates for eRecruitment

Milestones:

Milestone Due Date
End of Planning (Project Brief - Phase 1) 24-Aug-2018   
Start of Business Analysis 27-Aug-2018
End of Analysis / Design 14-Sep-2018
Start Data Anonymisation (Phase 1) 05-Oct-2018
Complete Data Anonymisation (Phase 1) 12-Oct-2018
Deliver Phase 2 Recommendation and Estimate For Review    12-Oct-2018
Deployment Phase 1 - Sign-Off 26-Oct-2018
Phase 2 Recommendation and Estimate Decision / Sign-Off 26-Oct-2018
Project Closure - Phase 1 02-Nov-2018

 

RAG Status

GREEN

 Project  report by Ken Miller for September 2018

Achievements this Period

  • Clarification from the business with regards phase 1 fields to be de-identified.
  • Phase 1 business analysis on-going to complete BRD. 
  • Systems analysis and design on-going.

Issues

  • Delay in clarification of fields to be de-identified impacted completion of analysis documents.  This has now been resolved.

Next Steps

  • Business to sign off BRD.
  • NEWSTEST and NEWSDEV environments to be refreshed from live prior to integration testing and UAT.
  • Budget  and milestones to be re-reviewed by the new Project Manager in line with ASTA / resource bookings.
  • Define / analyse the requirements for Phase Two - Historical job application data in eRecruitment and associated universes.

 

Section Four: Closed or Withdrawn Projects

 

AttachmentSize
Image icon hrs-res-sep18.jpg72.76 KB
Image icon hrs-flook-sep18.jpg89.42 KB