Data Safe Haven - Achieving ISO 27001

Current project status

Report Date RAG Budget Effort Completed Effort to complete
January 2020 AMBER 0.0 days 0.0 days 0.0

Project Info

Project
Data Safe Haven - Achieving ISO 27001
Code
RSS042
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
Anthony Weir
Current Stage
Deliver
Status
In Progress
Project Classification
Transform
Start Date
08-Oct-2018
Planning Date
31-Jan-2019
Delivery Date
29-Nov-2019
Close Date
31-Dec-2019
Overall Priority
Higher
Category
Compliance

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.