Report for July 2018

Report Date
July 2018

Achievements this period

Good progress was achieved in terms of the technical deliverables of  the the project.  The search widget was designed and built and is capable of being incorporated onto any of the universities web pages.  This proof concept (POC)  is capable of being further developed and implemented as a minimum viable product (MVP) when the underlying data is of suitable quality. 

There are technical issues with getting the right data in the right format from the Funnelback collection.   Rectifying this problem will delay the the delivery of the application and the impact of this means that it will not be possible to deliver the project to the agreed plan.  The Funnelback issues are being supported by the vendor.  At the same time,  the data quality of staff profiles held within Pure are inconsistent and some of the key data is missing.  This means that data being delivered to the search results page is not at the level that could enable the application to be deployed in production.  Both these issues prevent the search application from going live at this time.  Risks and issues are raised to cover these problems.

Notwithstanding this, development work is ongoing with Funnelback by the LTW team and Student Recruitment  are continuing to drive data and standards development beyond the end of the project as both of theae areas are of strategic interest to the teams.   Aditionally, further funding is being sought b Student Recruitment, through a number of channels, to complete any remaining search result page development.

Student Recruitment are also driving forward with standards guidance and policies to improve the quality of staff profiles to enhance the supervisor search journey and ultimately the data quality.  

Issues

  • None

Next steps

As this is a core funded project it is not possible to move funding into the new academic year the project will be closed.

Milestones

Target Datesort descending Previous Date Title Stage Complete
31-Aug-2017  30-Jun-2017 End of Planning Plan Yes
05-Feb-2018 No date available       Unsuspend project and Kick off the development work Execute No
11-May-2018 23-Mar-2018 End of Planning (re-plan following suspension) Plan Yes
25-May-2018 No date available System Design - Research PURE API Design Yes
19-Jun-2018 No date available Build Complete Build Yes
03-Jul-2018 No date available Integration Complete Integrate                  No
18-Jul-2018 No date available Acceptance Complete Accept No
26-Jul-2018 No date available Deployment Deliver No
14-Aug-2018 No date available Project Closure Close No
         
External Milestones        
21-Dec-2018 21-Dec-2017 Guidance policy for use of "Willingness to take Ph.D. students" and "Ph.D. research projects available"         
21-Dec-2018 11-May-2017 Guidance policy for use and tagging of keywords to support PGR search
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
RED
Overall
RED
RAG Commentary
Issue - Current issues with Funnelback search engine retrieval and Pure data quality are ongoing and preventing the project from delivering major milestones and going live. Reduction in scope to Minimum Viable Product is needed to complete the project within the allocated budget and time frame because core funding is only available in session 17/18.
Change Status
Activity
Approved budget
100.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.