Report for July 2018

Report Date
July 2018

Status:

Both workshop reports virtually complete - just final presentation decisions being discussed. Expected to complete within a few days.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days