Project Brief

 

Document Sign-off

Name Role Date signed off
David Fergusson Project Sponsor  
Andrew Todd Project Manager  
Maurice Franceschi Programme Manager  

 

 

Background

As part of the annual Research Infrastructure Refresh budget. £340k was assigned to the purchase of nodes to be assigned to the Openstack Cloud.

These should be purchased and implemented by the end of financial year.

Scope

Purchase Compute nodes to the value of £340k for the use of the Openstack Cloud.

Nodes to be located at the ACF Data Centre with the other Openstack Cloud Infrastructure.

Have the purchase complete and receipted (i.e. the kit onsite) by the end of the financial year.

 

Out of Scope

Removal of any historic nodes. This project it essentially adding nodes. Not replacing or refreshing.

A refresh strategy needs to be agreed at a strategic level before it can be implemented at Project level. 

 

Objectives and Deliverables and Success Criteria

  Description of the Objective Success Criteria
     
Define an Order Buy £340k worth of Compute Nodes as per  Specification agreed with the Research Systems Team.  Specification Agreed with Research Systems Team and Appropriate kit ordered. 
      
Deliver Have Kit delivered and receipted before end of Financial Year. Order Receipted before the end of Financial Year.
      
Instal and Configure Nodes installed in the racks and available to the Openstack Service for use. Available for use by the end of July.

  

   

 

 

Requirements

Guidance (please remove)

State the known requirements that drive the project.

Who has set this requirement (who owns the requirement).

Ideally we set these as MoSCoW:

MUST - we would see the project as failing totally or partially if these are not achieved

SHOULD - we have a high expectation that these will be doable with planned work and budget - but if necessary these can be descoped

COULD - if all goes very well, these might be possible

WON'T - we want to be explicit about certain things that people might expect us to deliver but we want to be clear we won't deliver

Which deliverables will fully or partially satisfy the requirement?

 

Requirement User / Owner MoSCoW Associated Objective/Deliverable (Ox/Dx.x)
       
       

 

Benefits

This project will make xx additional nodes available to the Openstack Cloud Platform.

These will be delivered by the end of the Financial year.

 

Project Team

Role Name Division / Group / Team / College / School and Title
Project Manager Andrew Todd  
Technical Lead Kevin Tomlinson  
Additional Technical. Jan Winter  

                          

 

 

 

 

Project Info

Not available.

Documentation

Not available.