May 2018 - Project Update

Report Date
May 2018
Report Date
May 2018

Achievements

  • Delivery of first draft of standards and technology landscape review in Wiki pages.

Issues

  • No issues to report

Next Steps

  • Finalise deliverables.
  • Arrange a Hackathon event to communicate and pilot the standards and guidance in the wiki pages.

Budget Information

  • Current spend £186
  • Estimated spend £6, 000
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days