Report for May 2018
- Report Date
- May 2018
Resource Position
The resource position does not reflect current discussions on required changes for:
- FIN118: Project to be closed and budget to complete the upgrade this year and next is to be moved to FIN124.
- FIN119: The transfer of budget from Procurement Programme to cover additional Core budget requirement. This will increase budget this year to 116 days.
- FIN123: This project is due to complete planning with an increased estimate of 49 days for the project this year.
- FIN124: Core / Sponsor Funded (tbc) budget to progress project to closure - see FIN118
The above will be reflected in the June Resource Position.
Forward Look
Section 2: Projects Not Started
Project Info | Programme Managers Commentary |
FIN121 eTime 17/18 (eSignature) Planning - tbc Delivery - tbc RAG Status : Amber |
Currently suspended - to be closed. |
FIN124 eFin Upgrade Planning - tbc Delivery - tbc RAG Status : Green |
Project FIN124 has been opened to replace FIN118 to:
The closure report for FIN118 and development and sign off for FIN124 brief will be completed in June 2018. |
Section 3: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
FIN118 (AP56-016) eFinancials upgrade Core funded Expected milestones across the closure of FIN118 and opening of FIN124:
RAG Status: Amber
|
Report by Chris Orrell
Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||
FIN119 (AP67-024) eInvoicing
RAG Status : AMBER
|
Report by Richard Bailey
For reference: SG = Scottish Government, SGS = Scottish Government Solution Achievements this Period
Issues
Next Steps
RAG CommentaryChange: The change to the project timescales and moving a proportion of the development to the 2018-19 Financial Year creates a risk around securing budget to complete the tasks required in that year as budgets for 2018-19 are not yet agreed / set. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||
FIN123 (AP56-016) Annual Finance Document Revitalisation 17/18
Core funded
RAG Status : GREEN |
Report by Lee-Ann Simpson
Achievements
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||
Section 4: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
FIN116 (AP67-022) eTime - guaranteed hours Category: Discretionary |
Project Manager - Richard Bailey Project closed 15th September 2017 |
FIN117 (AP56-054) Finance BI Improvement Category: Discretionary
|
Project Manager - Richard Bailey Project closed 4th August 2017 |
FIN108 (AP56-042) Essential enhancements (FIS) Category: Discretionary |
Project Manager - Emma McNab Project Closed 6th October 2017 |
FIN 120 (AP67-025) Fraud protection for Accounts Payable Category: Discretionary |
Project Manager - Emma McNab Project Closed 12th January 2018 |
FIN122 Decommissioning ABS Expense System |
Project Manager - Emma McNab Project Withdrawn 2nd February 2018
|