April 2018

Report Date
April 2018

Achievements in last period

  • Project Closure meeting with project sponsor and senior stakeholders
  • Booking for decommission of live system on 07/05/2018.

 

Next Steps

  • Decommission and Live environment.
  • Close project
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Change: project closure milestone delayed to allow business more time to sign off data extract
Change Status
Activity
Approved budget
370.0 days
Activity this month
1.0 day
Activity this year
23.0 days
Activity to date
364.0 days
Estimate to complete current year
2.0 days
Estimate to complete future years
0.0 days