Report for August 2017

Report Date
August 2017

Achievements in Last Period

  • DR testing completed successfully.
  • IDM Dashboard Migration completed and as the last deliverable the Delivery milestone has been marked complete.

Issues

 

Next Steps

  • Initiate project closure ready for 29 September.
  • Budget swap with HSS014 still to be completed.
Target Datesort descending Previous Date Title Stage Complete  
16-Dec-2016 04-Nov-2016 Planning Plan Yes

view

26-Jan-2017 No date available Start of iteration 1 Execute Yes

view

10-Feb-2017 13-Jan-2017 Foundation Stage Analyse Yes

view

22-Feb-2017 No date available End of iteration 1 Execute Yes

view

22-Feb-2017 No date available Iteration 1 Release Deliver Yes

view

01-May-2017 No date available Start of iteration 2 Execute Yes

view

08-May-2017 No date available Start of iteration 3 Execute Yes

view

12-May-2017 No date available End of iteration 2 Deliver Yes

view

18-May-2017 No date available Start migration of IDM dashboard Execute Yes

view

05-Jun-2017 No date available Start of iteration 4 Execute No

view

07-Jun-2017 No date available End of iteration 3 Execute Yes

view

07-Jul-2017 No date available End of iteration 4 Execute No

view

18-Aug-2017 No date available Completion of migration of IDM Dahsboard Deliver Yes

view

25-Aug-2017 21-Jul-2017 Delivery Deliver Yes

view

29-Sep-2017 28-Jul-2017 Closure Close No

view

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
GREEN
RAG Commentary
Cost is rated amber only to reflect the fact a budget swap is still to be completed, which explains the 26 days unallocated.
Change Status
Activity
Approved budget
122.0 days
Activity this month
3.4 days
Activity this year
3.4 days
Activity to date
98.1 days
Estimate to complete current year
9.3 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.