Report for August 2017

Report Date
August 2017

Achievements in Last Period

  • Alma workflow fix released to production on 6th Aug
  • Projectcompletion report updated with comments and signed off
  • Closure report submitted for Internal IS Apps approval on 18th Aug 
  • Information regarding automated course code data to be passed to DTI Enterprise APIs team for assessment and prioritisation

Issues

  • N/A

Next Steps

  • N/A

The project status is BLUE closed

 

   

 

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
100.0 days
Activity this month
0.2 days
Activity this year
92.3 days
Activity to date
92.3 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days