Report for July 2017
- Report Date
- July 2017
Achievements in this reporting period:
- I1 - Communication between EUSU supplier MSL ltd and lead developer to verify solution.
- I5 - HSS to AHSS will be implemented with the Org Hierachy changes, scheduled for 3 Aug. This will complete this improvement.
- I9 - PPMD frontend decommissioning - following confirmation of work required a unidesk is now with Development Technology to complete the task on 3rd August
- I10 - Resource has not been available to progress any further this month.
- I11 - Resource has not been available to progress any further this month.
Resolved issues:
Open issues:
Next Steps:
- I1 - Develop solution and deploy
- I9- PPMD decommissioning - there will be a requirement to decommission the BI reports in July of 2018
- I10 - Seek agreement for some continuation within Continuous Improvement 17/18
- I11 - Seek agreement for some continuation within Continuous Improvement 17/18
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days