Report for July 2017

Report Date
July 2017
  • Achievements this period:
    • Technical work progressing (note: This has been delayed due to staff absences but Edina are confident that this will not adversely affect our time scales).
  • Issues
    • Completion of work has extended by 3 weeks due to year end impact on Edina resources.
  • Next Steps
    • Complete technical build    
  • Milestones:
    • Core  planning complete  end of May 2017 - complete.
    • Build complete 07 July 2017 - this has run over and is now due to be complete 11 Aug.
    • Testing and assurance checks completed and signed off - infrastructure ready - 31/07/2017 - - this has run over and is now due to be complete 18 Aug.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
145.0 days
Activity this month
5.0 days
Activity this year
15.0 days
Activity to date
15.0 days
Estimate to complete current year
130.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.